Bid security is usually only 0.5% to 1.5% of the package price, but for a contractor bidding several packages at once, one wrongfully retained bond is not just lost money — it locks up guarantee credit lines at the bank for later packages. The good news is that Clause 9, Article 14 of Bidding Law No. 22/2023/QH15 lists, exhaustively, the cases where bid security is not refunded. Outside that list, a forfeiture has no legal basis.

The closed list in Clause 9, Article 14: test each point

Under Clause 9, Article 14 of the 2023 Bidding Law, bid security is not refunded only where: the bidder withdraws its bid, or writes to refuse work it proposed, after bid closing and while the bid remains valid; the bidder commits an Article 16 violation or another bidding-law violation leading to cancellation under Article 17; the bidder fails to provide the performance security required by Article 68; the bidder fails to enter, or refuses, contract negotiation within 05 working days for domestic bidding (10 days for international) from the negotiation invitation, force majeure excepted; the bidder fails to finalise the contract within 10 days (20 days international) from the award notice, force majeure excepted; or the bidder fails to sign within 10 days (20 days international) from contract finalisation, force majeure excepted. Every reason outside these six groups — a capacity-based elimination, simply not winning, or the owner cancelling for changed needs — is not a ground to keep the money.

In practice, wrongful-forfeiture cases cluster into three patterns. Pattern one: the owner retains the security claiming the bidder “refused to finalise”, when in fact the bidder attended finalisation and the parties disagreed because the owner changed content versus the bidding documents and the bid — force majeure and owner non-compliance with finalisation principles are recognised in Decree 24/2024/ND-CP when handling next-ranked-bidder situations. Pattern two: the guarantee is called after its validity has expired, or the payment demand lacks the documents the guarantee itself requires. Pattern three: the security is kept after the package was cancelled for reasons unrelated to the bidder, with the owner simply going silent on release requests.

Recovery in the right order: confront, petition, then sue

The first step is always a confrontation letter: the bidder asks the owner and the bid solicitor to identify exactly which point of Clause 9, Article 14 the retention rests on and the evidence for the triggering event, attaching its own file — finalisation minutes, correspondence around the 05- and 10-working-day milestones, and the bank’s confirmation of the guarantee’s validity. Many cases end here, because the retention ground cannot survive being written down. If the reply is unsatisfactory, the bidder uses the petition mechanism in Articles 89 to 91 of the 2023 Bidding Law for issues arising during contractor selection, with a parallel letter to the competent person where the solicitor is a hired consultant.

Once the dispute is a pure money dispute, the forum is the civil court or arbitration where an applicable arbitration agreement exists. The claim should cover: full repayment of the amount collected, late-payment interest on the wrongfully held sum under Article 357 of the 2015 Civil Code, and the extra facility and guarantee fees caused by the locked security. Keep the bank’s role distinct: a bid guarantee is the credit institution’s independent undertaking; the bank pays against a formally compliant demand without judging the underlying dispute. So if a baseless call is imminent, the bidder must immediately consider asking the court for interim measures to prohibit or suspend payment, rather than only suing the owner after the money has moved.

Prevention for future packages

Three habits keep a contractor out of bid-bond disputes almost entirely. First, systematically archive every Clause 9, Article 14 milestone — dates of the negotiation invitation, the award notice and contract finalisation — with proof of sending and receipt. Second, put every refusal or disagreement during contract finalisation in writing, with reasons tied to content the owner changed versus the bidding documents, so it cannot be recorded as a “refusal to finalise”. Third, chase release deadlines right after results: the security of unsuccessful bidders, and of the winner once performance security is lodged, must be refunded or released under Article 14, and any delay should be chased by a receipt-stamped letter.

Frequently Asked Questions

On what basis can a wrongfully forfeited bid bond be recovered?

The central basis is Clause 9, Article 14 of the 2023 Bidding Law, which exhaustively lists the non-refund cases. The bidder requires the owner to identify which listed point the retention falls under; if it falls under none, the forfeiture lacks basis and the bidder may reclaim the amount plus late-payment interest under Article 357 of the 2015 Civil Code.

When is bid security lawfully kept?

The six groups in Clause 9, Article 14 of the 2023 Bidding Law: withdrawal after closing; an Article 16 violation leading to cancellation; failure to lodge performance security; refusal of negotiation beyond 05 working days (domestic); refusal to finalise beyond 10 days; and refusal to sign beyond 10 days after finalisation — force majeure excepted throughout.

If the bank has already paid the owner, who do you sue?

The owner, to recover the baselessly collected amount — the bank performs an independent guarantee against a formally compliant demand and does not decide the underlying dispute. If the money has not yet moved, the bidder should seek interim court measures to stop payment in parallel with the dispute against the owner.

Where do you sue over a retained bid bond — petition first?

Follow the order: a confrontation letter testing Clause 9, Article 14; a petition under Articles 89 to 91 of the 2023 Bidding Law if selection is still in progress; then a civil suit in the competent court or arbitration where an applicable agreement exists. This sequence builds the evidence file and avoids procedural objections.