Steel, cement and fuel climb together and material prices are up 30% after the bid contract was signed: the contractor asks for a price adjustment, the owner replies “lump sum — the price does not move”. Both sides are half right. The right to adjust does not live in the percentage increase; it lives in the contract type signed under Article 65 of Bidding Law No. 22/2023/QH15 and in whether a price-adjustment clause exists in the contract at all.
Contract type decides 80% of the negotiation
The 2023 Bidding Law distinguishes contract types with contractors, three of which carry price risk directly. Lump-sum contracts: the contract price does not change throughout performance, and the contractor was required to price market-fluctuation risk into its bid — the worst position for an adjustment request, where the only doors left are out-of-scope additional quantities or owner-instructed changes. Fixed unit-price contracts: unit prices stay fixed but payment follows actually accepted quantities; market-price risk still sits with the contractor, though disputes tend to migrate to quantities. Adjustable unit-price contracts: unit prices are adjusted by the formula and input factors agreed from the start — the only type with a contractual “automatic” adjustment mechanism, where the contractor’s job is simply to gather indices, apply the formula and file the adjustment correctly each period.
For construction contracts, Decree 37/2015/ND-CP on construction contracts adds its own layer: construction contract prices are adjusted only where the contract so agrees, following the agreed content and formula; escalation-based adjustment must rest on price indices or material prices published by competent authorities. Negotiation practice in Vietnam shows state-funded owners struggle to accept extra-clause adjustments not from ill will but because audit and inspection will later trace the legal basis of every extra dong. Understanding this calibrates expectations: out-of-clause negotiation succeeds mainly in private projects, or in forms that do not move the nominal price.
Where the contract is silent: Article 420 is a narrow but real door
Article 420 of the 2015 Civil Code governs performance when circumstances change fundamentally: if circumstances change for objective reasons arising after contracting, unforeseeable at signing, and continued performance on the old terms would cause serious loss to one party despite that party having taken every necessary measure within its ability, the injured party may require the other to renegotiate the contract within a reasonable time. The four conditions are cumulative and hard to satisfy together: a 30% rise in one material group is not necessarily a “fundamental change” where price volatility is an ordinary business risk of construction, or where a lump-sum contract expressly allocated price risk to the contractor. If renegotiation fails, the requesting party may ask the court to terminate or to amend the contract to rebalance interests — but courts amend only in special cases, and termination still leaves payment for work done and losses to allocate. Article 420 is therefore serious negotiation leverage, not a guaranteed adjustment ticket.
Negotiation strategy: sell the owner a plan, not a complaint
An effective negotiation file has three evidence layers: objective price movement (quotations from at least three suppliers at two points in time, the local construction price index where available, manufacturers’ increase notices); quantified impact on the package (the rising materials’ share of the contract price, the absolute cost overrun, the package’s break-even point at unchanged prices); and a sharing proposal instead of full transfer — for example the owner adjusting only the portion of materials exceeding an agreed percentage threshold, or compensating through schedule extension so the contractor can wait out prices, with corresponding security extensions, or rebalancing quantities between work items. Sequence the asks: protect the schedule and avoid delay penalties first, reduce losses through partial adjustment second, and only if both fail consider termination under Article 420 or the contract’s termination clause — with a clear analysis of exit costs for both sides, which is the contractor’s strongest negotiating card.
One final warning: never stop work unilaterally to “apply pressure” without a termination ground. An ungrounded stoppage converts the contractor from injured party into breaching party, opening the door to delay penalties, a call on the performance security under Article 68 of the 2023 Bidding Law, and termination for contractor fault.
Frequently Asked Questions
If material prices rise 30%, can the bid contract price be adjusted?
It depends on the contract type under Article 65 of the 2023 Bidding Law and the adjustment clause: adjustable unit-price contracts apply the agreed formula; lump-sum and fixed unit-price contracts in principle do not move, except for out-of-scope additions or owner changes. Outside the clause, the only door is renegotiation under Article 420 of the 2015 Civil Code where all four fundamental-change conditions are met.
What file should a price-adjustment negotiation carry?
Three evidence layers: objective price movement (supplier quotations at two points in time, the local construction price index, manufacturers’ notices); quantified package impact (materials’ share of the contract price, absolute overrun, break-even at unchanged prices); and a concrete risk-sharing proposal such as adjusting only the above-threshold portion, extending the schedule, or rebalancing quantities.
If the owner refuses adjustment, can the contractor terminate?
Only on a contractual termination ground, or through Article 420 of the 2015 Civil Code: if renegotiation fails, ask the court to terminate or amend the contract. Stopping work or walking away to apply pressure is treated as breach, risking penalties, a call on the performance security under Article 68 of the 2023 Bidding Law, and termination for contractor fault.
Do construction contracts have their own price-adjustment rules?
Yes. Decree 37/2015/ND-CP on construction contracts allows price adjustment only where the contract agrees it, following the agreed content and formula; escalation adjustments must rest on price indices or prices published by competent authorities. That is why adjustment files for state-funded projects must anchor tightly to the clause and official indices.
Related articles
- Actual Timelines at the Business Registration Office: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Tax Department: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Department of Natural Resources and Environment: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Department of Construction: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Department of Education and Training: Statutory Days vs Reality, and Where Delays Happen
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.