The “24 months” in land recovery decisions comes from Article 81(8) of Land Law 31/2024/QH15: land allocated or leased for an investment project that is not put to use within the prescribed time, or whose use is 24 months behind the schedule in the approved investment project, receives a 24-month extension of use on payment of a sum corresponding to the land levy or rent for the delayed period; if the land is still not in use when that window closes, the State recovers it without compensation for the land and assets attached to it, force majeure excepted. The piece on contributed land partly recovered (FDI-LC-4787) handles the civil fallout between capital contributors; this article covers only the relationship with the State — how the clock runs, which objective causes save land, and how to negotiate before a recovery decision is signed.
Where the 24-month clock starts
Two clocks must be separated. The first runs from handover of the land on site: a project that leaves land unused for a long continuous period is inspected and minuted by the natural resources authority. The second is the schedule clock: land use running 24 months behind the approved investment project schedule triggers the paid 24-month extension mechanism. Companies often lose at this stage because the schedule in their investment file was written over-optimistically at application, becoming a legal trap for themselves five to seven years later.
When inspection minutes are drawn up, what decides the outcome is not oral explanation but the evidence file on the causes of delay: unfinished site clearance by the locality, planning adjustment decisions, suspension orders by state bodies, or certified force majeure. Inspection minutes are the root document for any later complaint, so sign them with reservations recorded and file the full evidence set at the inspection itself.
Accepted and rejected objective causes
Practice accepts three groups: site clearance delays attributable to the State or to landholders who have not handed over; planning or policy changes forcing project redesign and re-procedure; and certified force majeure such as natural disasters or epidemics. Not accepted: funding shortfalls in the investor’s own arrangements, waiting for land prices to rise, or a change of business intent — the group that makes recovery decisions survive complaints.
Even a genuine objective cause loses most of its force if the company never notified the licensing authority in writing during the delay: the duty to notify and seek schedule adjustment lies on the investor, and years of silence are read as abandonment of the project.
Negotiating to keep the land, and rent already paid
Effective negotiation happens before the recovery decision issues, around a package: accept payment for the delayed period under the Article 81(8) mechanism, commit to completion milestones backed by financial assurance, and offer to return the area with no immediate use plan in order to keep the core. Once a recovery decision has issued, the route is complaint under Complaint Law 02/2011/QH13 or administrative litigation under Law on Administrative Proceedings 93/2015/QH13, with a request to suspend enforcement to preserve the status quo.
Rent already paid for periods of lawful use is not refunded. For recovery on the Article 81(8) violation ground the principle is no compensation for the land, and amounts paid for unused periods and assets on the land are dealt with in the recovery decision and the compensation rules — refund expectations should be quantified cautiously by counsel from the outset.
FAQ
How long of non-use leads to recovery?
Under Article 81(8) of Land Law 31/2024/QH15, a project that does not put land to use, or whose land use is 24 months behind the approved project schedule, receives a 24-month extension on paying the corresponding amount; if the land is still unused at the end of that extension, the State recovers it without compensation for the land, except in force majeure cases.
What objective reasons are accepted?
Commonly accepted causes are site clearance delays, planning or policy changes forcing project adjustment, suspension decisions by state authorities, and certified force majeure. Lack of self-arranged funding, waiting for the market, or a change in the investor’s business plans are not objective causes and do not save a recovery decision.
Is paid rent refunded?
Rent for periods already used is not refunded. For recovery on the Article 81(8) violation ground, the principle is no compensation for the land and assets attached to it; treatment of amounts paid for unused periods and of assets on the land is determined in the recovery decision, so each item should be raised specifically by complaint or negotiation rather than assumed refundable.
Where do I file a complaint?
Complain first to the authority that issued the recovery decision under Complaint Law 02/2011/QH13; if dissatisfied, complain to the immediate superior level or bring an administrative lawsuit under Law on Administrative Proceedings 93/2015/QH13, with a request to suspend enforcement to preserve the status quo during resolution.
Related articles
- Wrongly Calculated Land Rent Disputes in Vietnam: Complaints and Refund Demands
- Industrial Park Land Lease Disputes in Vietnam: Unreasonable Fee Hikes and Unilateral Termination
- Project Land Deposit Disputes in Vietnam: Recovering Deposits Upon Seller Breach
- Overlapping Certificate Disputes in Vietnam: Administrative Lawsuits to Cancel Duplicates
- Environmental Penalty Disputes in Vietnam: Appealing Discharge Fines
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.