Scenario: the developer finishes a workshop for lease; the fire-suppression system is half installed, the fire-safety acceptance dossier not yet filed. The tenant — an FDI components maker — has signed orders and moved in machinery, and presses for a “temporary” handover to meet deadlines, promising to “complete it later”. Six months pass; the system is still unaccepted, the plant still runs at full capacity. Who is sitting on a legal time bomb — and when might it go off?
This is an especially serious violation, not an administrative oversight
Putting a structure subject to special fire-safety requirements into operation without the police’s written acceptance of the fire-safety commissioning results ranks as an especially serious violation under current law (the 2024 Law on Fire Prevention, Firefighting, Rescue and Salvage effective 1 July 2025 and Decree 105/2025/ND-CP). The direct consequence: the competent authority orders temporary suspension (up to 30 days), escalating to suspension if not remedied — the entire line stops, no “urgent orders” exception.
In parallel, the act draws administrative fines in the fire-safety sector under Decree 106/2025/ND-CP. And if a fire occurs causing casualties or property damage, “operating before acceptance” becomes clear evidence of violation for criminal prosecution under Article 313 of the 2015 Penal Code (as amended in 2017) — up to 12 years’ imprisonment. At that point, the oral promise to “complete it later” saves no one.
For the tenant: never sign a “temporary” handover while fire safety is incomplete
For the leasing company the risk is greater, since it cannot control the landlord’s acceptance progress. Under the 2015 Civil Code, the lessor must keep the leased property in a condition fit for the leased purpose throughout the lease term. A workshop without fire-safety acceptance is legally unfit for production operations — the tenant may:
- Demand the lessor complete acceptance within a set deadline, in writing;
- Suspend rent payment for the period the premises cannot be used (if operations halt under a suspension decision);
- Unilaterally terminate the lease and claim damages if the lessor fails to remedy — including machinery relocation costs, substitute workshop rent, and profits lost to disruption.
In practice, many FDI workshop leases contain a clause making “the tenant responsible for fire safety”. Such a clause cannot erase the project owner’s duty to obtain commissioning acceptance — that is the owner’s duty to the state regulator, not transferable by private contract.
The only way out: genuine acceptance, not paper-chasing
There is no shortcut. The proper sequence: the developer completes the system per the appraised design, files for acceptance, cooperates with the police’s physical inspection, and obtains the written acceptance. Any “acceptance paper” issued without physical inspection is a forged document — and after a fire, investigators reconcile the acceptance dossier against actual conditions within days.
For a tenant already “sitting” in an unaccepted workshop: send an immediate written demand to the developer, and assess your own risk — if fire breaks out, your own property insurer may deny the claim on the ground the facility operated in breach of fire law. Weighing order deadlines against the risk of total loss is less difficult than many directors think.
Related articles
- Actual Timelines at the Department of Natural Resources and Environment: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Tax Department: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Business Registration Office: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Industrial Park Management Board: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Department of Planning and Investment: Statutory Days vs Reality, and Where Delays Happen
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.