The environmental impact assessment is the first and heaviest environmental procedure in an FDI project’s life, because it must be completed and approved before the project is decided and implemented. Not every project needs a full EIA report: the law tiers projects by group and environmental sensitivity, and mis-tiering makes an investor either run an unnecessary multi-month procedure or miss a mandatory one and get halted midway.
The deciding criteria: project groups and sensitivity factors
Article 30 of Law on Environmental Protection 72/2020/QH14 places the EIA duty on group I investment projects, the group with high risk of adverse environmental impact under investment project classification, and part of group II projects carrying environmental sensitivity factors. Decree 08/2022/ND-CP, as amended by Decree 05/2025/ND-CP, supplies detailed lists and criteria by production type, capacity scale, land area and sensitive locations such as proximity to water sources, residential areas or protected zones.
In practice, a typical FDI factory in an industrial park in sectors like chemicals, textile dyeing, electroplating, paper making or processing with large wastewater and emissions almost always falls inside the EIA group. Conversely, a small assembly project with negligible waste may only need environmental registration or an environmental permit without a full EIA. Which tier applies must be determined by checking the statutory list against the concrete project file, not by inferring from the sector name.
Preparation, appraisal and the role of the EIA result
The EIA report is organised by the project owner through a qualified consultancy, identifying and forecasting impacts, mitigation measures, and an environmental management and monitoring programme, with consultation of communities and related authorities as required. Approval of the EIA appraisal result grounds the authority’s investment decision and forms the base for the later environmental permit, so every commitment in the EIA becomes a duty the project must perform in construction and operation.
EIA preparation and appraisal time is a significant component of the project’s total schedule, commonly counted in months once consultation, appraisal and council-requested corrections are included. Investors should place the EIA on the project’s critical path from the pre-feasibility stage rather than starting after site and design are fixed, because the EIA outcome can require changes to the project’s own location, technology or scale.
Consequences of proceeding without a required EIA
Implementing a project that belongs to the EIA group without an approved appraisal result is a central violation of environmental law: administrative fines at high levels for organisations under the environmental penalty decree, forced suspension of implementation, a duty to prepare and submit a supplementary EIA, and in many cases remediation of environmental consequences already caused. The project also cannot complete later procedures such as the environmental permit for operation.
EIA cost is market consultancy cost, varying strongly with project scale and complexity, covering environmental baseline surveys, sampling and analysis, report preparation and the statutory appraisal fee. Because the figure depends entirely on the concrete project, investors should obtain quotations from several qualified consultancies on the same terms of reference instead of trusting any average figure circulating in the market.
Frequently Asked Questions
Which FDI projects must prepare an environmental impact assessment?
Projects that must prepare an environmental impact assessment are group I investment projects with high risk of adverse environmental impact and part of group II projects with environmental sensitivity factors, under Article 30 of Law on Environmental Protection 72/2020/QH14 and the detailed list in Decree 08/2022/ND-CP as amended by Decree 05/2025/ND-CP. Determination follows the concrete project’s production type, capacity, land area and sensitive location.
What criteria decide whether an EIA is required?
The criteria have four factor groups: the pollution risk of the production or business type; capacity scale and land use area; the level of wastewater, emissions and hazardous waste generated; and the project’s location near sensitive receptors such as surface water sources, residential areas and protected zones. FDI projects in chemicals, dyeing, plating or high-emission processing almost always qualify; a small low-emission assembly project may need only environmental registration or a permit.
How much does an EIA cost?
EIA cost has no fixed state tariff; it is market consultancy pricing varying with project scale, complexity and the scope of baseline surveys and sampling. Beyond consultancy fees there is the statutory report appraisal fee. Investors should ask several qualified consultancies to quote on the same terms of reference for comparison, and budget this cost as part of investment preparation costs.
What happens if a project operates without an EIA?
A project in the EIA group that implements without an approved appraisal result faces high-level administrative fines for organisations under the environmental penalty decree, forced suspension of implementation, a duty to prepare and submit a supplementary EIA and remediation of consequences. The project simultaneously fails the conditions for an environmental permit for the operating phase, so the whole legal route is blocked at the violation point.
Bottom line for project investors
Determining whether a project needs an EIA is the first environmental step of every FDI project, and it must be settled by checking the statutory list against the concrete project file. Settling it correctly at pre-feasibility turns the EIA into part of the plan instead of an obstacle appearing midway.
Related articles
- Housing for Armed Forces and Official Housing in New Urban Planning: Distinguishing From Commercial Social Housing
- Preferential Loans for Social Housing Projects via the VND 120 Trillion Credit Package: Loan Conditions and Progress-Based Disbursement
- Condominium Management Board Disputes and the 2% Maintenance Fund: Guidance for Foreign Developers in Mixed-Use Projects
- Condotels and Officetels: The Certification Framework and Ownership Terms After New Guidance
- Serviced Apartments and Short-Term Stays (Homestay/Airbnb Models) in Condominiums: The Legal Line Under the 2023 Housing Law
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.