When a contract dispute goes to VIAC arbitration, the first question most businesses ask is: how long will it take to get an award? The answer has two layers. As a matter of statute, there is exactly one hard deadline: the arbitral tribunal must render the award no later than 30 days after the final hearing session (Article 61.3 of the 2010 Law on Commercial Arbitration). In practice, a VIAC arbitration typically runs 6 to 12 months from filing to award.

This article breaks down the timeline stage by stage, identifies what stretches it out and how to shorten it, and compares arbitration timing with court litigation so businesses can choose the right forum.

The only statutory deadline: 30 days to render the award

The Law on Commercial Arbitration 54/2010/QH12 (effective 1 January 2011, still in force) sets no overall maximum duration for arbitral proceedings. It imposes a single deadline in Article 61.3: the tribunal shall render the award within 30 days from the date of the final dispute-resolution hearing.

Two legal consequences follow:

  • Arbitral awards are final (Article 61.5): they take effect immediately and, unlike court judgments, cannot be appealed. This finality is the main reason arbitration is considered significantly faster than the first-instance plus appellate court route.
  • There is no statutory “6-month maximum” in the Law on Commercial Arbitration. The frequently quoted 6–12 months reflects VIAC practice, not a legal time limit.

The five stages of a VIAC arbitration

Stage 1 — Filing and docketing (1–2 months)

The claimant files the statement of claim with supporting documents and pays the advance on arbitration fees. VIAC checks the file for completeness and notifies the respondent, who then has a deadline to submit a statement of defence. This stage usually takes 1–2 months and can stretch if documents are missing or the respondent is abroad.

Stage 2 — Constitution of the tribunal (1–3 months)

The parties agree on the number of arbitrators (one or three) and select them. If they cannot agree, the VIAC Chairman appoints. This is the stage most prone to deadlock and can take 1–3 months when the parties disagree on appointments.

Stage 3 — Preparation, exchange of evidence (2–4 months)

The tribunal holds a preparatory meeting, sets the procedural timetable, and the parties exchange submissions, evidence, expert opinions and, where needed, independent assessments. Technically complex cases (construction, technology transfer) typically spend 2–4 months here.

Stage 4 — Hearing sessions (1–2 months)

The tribunal holds hearings for presentations, argument and witness examination. Complex cases may require multiple sessions. After the final session, the tribunal deliberates.

Stage 5 — Rendering the award (maximum 30 days)

The only stage bound by a statutory deadline: 30 days from the final hearing (Article 61.3 of the 2010 Law on Commercial Arbitration). The award is delivered to the parties and takes effect immediately.

StageContentIndicative duration
1Filing, docketing1–2 months
2Constitution of the tribunal1–3 months
3Evidence exchange, preparation2–4 months
4Hearing sessions1–2 months
5Award (statutory deadline)Max. 30 days
Total in practice6–12 months

Note: the 6–12 month range reflects VIAC practice, not a statutory limit. Simple cases with clean evidence can finish in 4–6 months; complex multi-party or cross-border cases may exceed 12 months.

Five factors that stretch an arbitration out

  1. A sloppy arbitration clause: no designated institution, no agreed number of arbitrators, no language of proceedings — the parties then spend months agreeing on issues that should have been settled at signing.
  2. Deadlock over tribunal appointments: each side wants “its” arbitrator, stalling constitution.
  3. Complex evidence requiring expert assessment: construction and technology disputes often need independent assessments, lengthening preparation.
  4. Deliberate delay tactics: late filings, absence from hearings, repeated extension requests.
  5. Foreign elements: service of process abroad, translation, and application of foreign law all add time.

Four ways to shorten the proceedings

  1. Use a complete model arbitration clause from day one: “Any dispute arising out of or in connection with this contract shall be settled by arbitration at the Vietnam International Arbitration Centre (VIAC) in accordance with its Rules of Arbitration; the tribunal shall consist of a sole arbitrator; the language of the arbitration shall be Vietnamese; the seat of arbitration shall be Hanoi (or Ho Chi Minh City).” A complete clause can save 2–3 months at Stage 2.
  2. Agree on a sole arbitrator for disputes of moderate value instead of a three-member tribunal.
  3. File a complete evidentiary record with the claim: the contract, appendices, acceptance minutes, email exchanges, payment records — arranged chronologically.
  4. Proactively propose an expedited procedural timetable and cooperate on early hearing dates.

Arbitration vs. court: a timing comparison

CriterionVIAC arbitrationCourts (first instance + appeal)
Typical duration6–12 months12–36 months (if appealed)
Statutory anchor30 days to render the award after the final hearing (Art. 61.3)The Civil Procedure Code sets preparation time limits per level
AppealNone — awards are final and effective immediatelyYes — a first-instance judgment is not effective if appealed
ConfidentialityHigh — hearings are not publicLimited — public trial is the principle

Arbitration’s biggest timing advantage is finality: no appellate round adding another 1–2 years as in court litigation.

After the award: enforcement and annulment

An arbitral award is enforceable immediately. If the losing party does not comply voluntarily, the winning party may request civil judgment enforcement authorities to enforce it compulsorily, like a court judgment. Within 30 days of receiving the award, a dissatisfied party may petition a court to annul it, but only on narrow statutory grounds (e.g., an invalid arbitration agreement, an improperly constituted tribunal, or a breach of the fundamental principles of Vietnamese law).

Frequently asked questions

Does the law cap arbitration at 6 months?
No. The 2010 Law on Commercial Arbitration sets no overall maximum. The only deadline is the 30-day award period after the final hearing (Article 61.3). The 6–12 month figure is VIAC practice.

Can an arbitral award be appealed?
No. Arbitral awards are final and effective immediately (Article 61.5). A court may only annul an award within 30 days on narrow grounds.

Can arbitration finish in under 6 months?
Yes, with a complete arbitration clause, a sole arbitrator, a clean evidentiary file and cooperative scheduling.

Is VIAC the only arbitration centre in Vietnam?
No. Vietnam has several arbitration centres, but VIAC is the largest and oldest, and the most frequently chosen by domestic and foreign businesses.

Legal basis

  • Law on Commercial Arbitration 54/2010/QH12 (effective 1 January 2011, still in force): Articles 61.3 and 61.5.
  • Decree 63/2011/ND-CP on state management of commercial arbitration.

See more articles on dispute resolution and arbitration.

Need help drafting an arbitration clause or facing a contract dispute? Contact FLAT Law Firm via our contact page.


The information in this article is general in nature and does not constitute legal advice. The status of cited instruments was verified as of 14 October 2026.

Transparency: this article was prepared by the FLAW AI Legal Council using AI systems. This article is awaiting review by the QA Council and has not been reviewed by a practising lawyer.