Foreign Investment

Moving Contracts and Orders From Your China Entity to Vietnam: What Novation Requires

Moving Contracts and Orders From Your China Entity to Vietnam: What Novation Requires

The Vietnamese plant is built — now the contracts and orders must move from the Chinese company. A quick “heads-up” won’t do: a contract is a three-party legal relationship (you – the counterparty – the new company) needing a proper novation. This article guides.

1. Novation vs assignment

  • Novation: replacing a contract party with a new one — needs all parties’ consent;
  • Assignment: transferring rights only (not obligations) — consent sometimes unneeded;
  • Practice: moving production orders needs novation — both rights and obligations shift;
  • Effect: novation extinguishes the old party’s obligations — the new party takes over fully;
  • In writing: novation agreements must be written — signed by all three.

2. Will customers accept the entity switch?

  • Reality: most customers accept — if quality and schedule hold;
  • Blocking clauses: anti-assignment clauses — some contracts forbid party changes;
  • Blocking clauses: change-of-control — customers may terminate;
  • Handling: negotiate early — not when shipping;
  • Assurance: parent-company performance guarantees — building trust.

3. Long-term framework agreements: renegotiating price?

  • Issue: old prices reflect Chinese costs — Vietnamese costs differ;
  • Opportunity: novation is a chance to renegotiate — sharing lower costs;
  • Risk: customers squeezing — “Vietnam is cheaper, cut prices”;
  • Prepare: compute the new cost base before negotiating — know breakeven;
  • Strategy: hold prices initially — then phase reductions.

4. Risks of producing in Vietnam under Chinese contracts

  • Tax: revenue booked in China but produced in Vietnam — dual tax risk;
  • Customs: goods exported from Vietnam but invoiced by the Chinese company — customs suspicion;
  • Liability: product defects — who’s liable? The contracting company or the producing plant;
  • Cash: money to Chinese accounts — the Vietnamese company starved of cash flow;
  • Bottom line: this model is only temporary — novate promptly.

5. Phased transition

  • Phase 1: new orders — signed directly with the Vietnamese company;
  • Phase 2: ongoing orders — novate contract by contract;
  • Phase 3: framework agreements — renegotiate and re-sign;
  • Priority: move big customers first — they need audit time;
  • Parallel: both entities coexist for a while — no disruption.

6. Novation paperwork

  • Tripartite agreement: China company – Vietnam company – counterparty — fully signed;
  • Content: terminating the old relationship, establishing the new — transition terms;
  • Receivables: reconcile old balances — who pays, who collects;
  • Warranty: warranty liability for old orders — clearly allocated;
  • Keep: originals — each party holds one.

7. Suppliers: novate too?

  • Rule: same as customers — purchase contracts need moving too;
  • Priority: strategic suppliers — key materials;
  • New terms: delivery location changes — new Incoterms;
  • Price: volume buying in Vietnam — negotiate better;
  • Localise: find Vietnamese suppliers — reducing dependence.

8. Tax of novation

  • Transfer: novation is not a sale — but taxes may arise;
  • Receivables: transferring balances — VAT treatment;
  • Assets: moving machinery and inventory along — import duty, VAT;
  • Advice: tax accountants review — no tax shocks from novation;
  • Plan: budget the tax cost of transition.

9. Common mistakes

  • Mistake 1: skipping novation — just shipping and invoicing via the China company;
  • Mistake 2: verbal novation — no paper, no evidence in disputes;
  • Mistake 3: forgetting old balances — uncollectable, unsettleable;
  • Mistake 4: forgetting warranties — customers claim against the new company, which blames the old;
  • Mistake 5: moving too fast — counterparties unready, disruption.

10. Novation checklist

  • All contracts to move — listed?
  • Anti-assignment clauses — reviewed?
  • Counterparty consent — in writing?
  • Balances and warranties — allocated?
  • Tax — computed?
  • Phased roadmap — ready?

11. Novation with banks and lenders

  • Loans: the Chinese company borrows working capital — the Vietnamese company needs fresh borrowing, not automatic succession;
  • Guarantees: the parent guarantees Vietnamese borrowing — accepted by Vietnamese banks;
  • Credit lines: build a new credit history — initially low limits;
  • Collateral: mortgage Vietnamese assets — register security transactions;
  • Warning: don’t starve the Vietnamese company of working capital during transition.

12. Insurance: switching the policyholder

  • Rule: insurance contracts attach to the purchasing entity — re-sign or convert;
  • Property: Vietnamese factory and machines — new policies;
  • Liability: product liability — coverage follows the producing entity;
  • Transition: no coverage gaps — an accident would be catastrophic;
  • Brokers: international brokers — global programmes for both entities.

13. Land and factory leases: can they be novated?

  • Leasing in Vietnam: the Vietnamese company signs fresh with the industrial-park developer — unrelated to Chinese leases;
  • Leasing in China: terminate early — negotiating early-termination fees;
  • Deposits: recover Chinese lease deposits — per contract terms;
  • Fixtures: dispose of improvements on leased land — who owns them;
  • Plan: synchronise Chinese lease exits with Vietnamese lease starts.

14. Disputes during the transition

  • Risk: during transition — whose responsibility is often blurry;
  • Clauses: novation agreements need clauses allocating past vs future liability;
  • Resolution: agree the mechanism — arbitration or courts, governing law;
  • Evidence: keep complete emails and minutes — transition periods lose trails;
  • Prevention: counsel reviews novation agreements before signing.

15. Novation and tax invoices

  • VAT invoices: after novation — the Vietnamese company issues Vietnamese VAT invoices;
  • Old invoices: reconcile invoices issued by the Chinese company before novation;
  • Cross-border: services between the two entities — invoice properly, withholding tax;
  • Timing: align invoicing with the novation effective date;
  • Records: keep both sets — tax audits will ask.

16. Communicating novation to counterparties

  • Letter: a formal notice — reasons, timeline, new contact points;
  • Meetings: meet key counterparties in person — not just email;
  • Assurance: guarantee continuity — same quality, same team;
  • FAQ: prepare an FAQ — payment details, contacts, procedures;
  • Follow-up: confirm receipt — don’t assume silence means consent.

17. Novation of IP licences

  • Licences in: technology licensed to the Chinese company — the Vietnamese company needs its own licence;
  • Licensor consent: ask the licensor — most allow intra-group transfers;
  • Royalties: withholding tax on royalties paid abroad;
  • Register: record the licence in Vietnam — if required;
  • Timing: don’t produce unlicensed — infringement risk.

18. Employment contracts: transferring staff with orders

  • Key staff: staff moving with the business — new Vietnamese contracts;
  • Seniority: recognise prior service — negotiated;
  • Benefits: align benefits — avoiding a two-tier workforce;
  • Non-competes: check enforceability under Vietnamese law;
  • Communication: tell staff early — rumours destroy morale.

19. Post-novation audit

  • Checklist: audit 90 days after novation — everything transferred;
  • Missed contracts: find stragglers — small contracts often missed;
  • Systems: update ERP, CRM — counterparty records;
  • Bank: update payment instructions — no money to old accounts;
  • Close: formally close the transition project.

20. Digital signatures on novation agreements

  • Validity: electronic signatures — valid if legal requirements are met;
  • Cross-border: three parties in different countries — e-signing speeds things up;
  • Evidence: audit trails — who signed, when;
  • Originals: keep certified copies — some authorities want wet ink;
  • Check: confirm each jurisdiction accepts e-signatures for novation.

21. Novation timeline template

  • Week 1–2: list all contracts — owners assigned;
  • Week 3–6: draft novation agreements — counsel reviews;
  • Week 7–10: negotiate with counterparties — signatures;
  • Week 11–12: systems updated — invoicing switched;
  • Week 13: audit — nothing missed.

22. Keeping the old entity alive during transition

  • Don’t rush: keep the Chinese entity operational — until novation completes;
  • Licences: maintain licences — don’t let them lapse mid-transition;
  • Staff: retain key staff — until handover is done.