“A pandemic broke out, we cannot deliver — this is force majeure.” “The war disrupted our supply chain, the contract must be suspended.” Declarations like these have proliferated since COVID-19, and more than a few are sham shields: partners invoking “force majeure” to legitimize non-performance when the real cause is rising input costs or a better-paying customer elsewhere.
Vietnamese law does not treat every pandemic or every war as automatic force majeure. This article gives you a 5-point checklist to verify a force majeure declaration — and how to respond when you catch a partner bluffing.
Legal framework (in force as of 17 October 2026)
- Civil Code 91/2015/QH13, Article 156.1: “A force majeure event is an event occurring objectively, which is unforeseeable and irremediable despite the application of all necessary measures and capabilities.” — Those two emphasized phrases are the entire test.
- Commercial Law 36/2005/QH11:
- Article 294: force majeure is one of the liability exemptions; the breaching party bears the burden of proof.
- Article 295: the breaching party must immediately notify the other party in writing of the exempting event and its possible consequences; failure to notify (or late notice) means damages remain payable.
- Article 296: in force majeure, parties may agree to extend performance deadlines; absent agreement, the deadline extends by up to 5 months (contracts ≤12 months) or 8 months (contracts >12 months); beyond that, either party may refuse further performance without damages.
Note: the burden of proof lies with the party invoking force majeure — not you. If your partner says “force majeure,” they must prove it; you only need to check their homework.
The 5-point verification checklist
Point 1 — Is the event real and objective?
Demand evidence of the event: government lockdown orders (for pandemics), official reports of armed conflict affecting shipping routes (for wars). “We heard there’s an outbreak in that province” is not evidence. Cross-check against authoritative sources: government portals, major news agencies.
Point 2 — Was it genuinely “unforeseeable” when the contract was signed?
This eliminates the most claims. Example: a contract signed in June 2022, when COVID-19 had run for over two years and global supply chains had adapted — invoking “pandemic force majeure” then is very hard to sustain, because pandemic risk was foreseeable and should have been addressed in the contract (hardship/price-adjustment clause). Likewise, an armed conflict dragging on for years is hard to call “unforeseeable” for contracts signed after it erupted.
Point 3 — Was it truly “irremediable” despite all measures?
Force majeure requires no alternative existed — not “the alternative cost more.” Counter-questions:
– Factory locked down — did the partner try renting another facility or subcontracting?
– Sea route affected by war — were land or air alternatives available (even pricier)?
– Pandemic-driven input shortage — were substitute sources available?
If a reasonable alternative existed and wasn’t tried, that’s not force majeure — it’s an economic choice, and economic choices don’t exempt liability.
Point 4 — Is there direct causation between the event and the non-performance?
The event must be the direct cause of the inability to perform. Counter-example: an outbreak hits Province A, but the partner’s factory in Province B operates normally and their inputs come from Country C, unaffected — then “the pandemic” doesn’t explain the non-delivery. Map the partner’s supply chain and test each link.
Point 5 — Did the partner notify immediately in writing? (Article 295)
This procedural trap catches many force majeure invokers. The law requires immediate written notice when the event occurs. If the partner went silent for 2 months then wrote “we’ve been under force majeure for 2 months,” they’ve breached the notice duty — and under Article 295, damages remain payable for the late notice. Always check the timeline: when did the event occur vs. when was notice sent.
Don’t confuse force majeure with hardship
A surprising number of partners use the wrong word for their real problem: they can still perform, but costs have exploded — 40% higher inputs, freight tripled. That is not force majeure (which requires impossibility), it is hardship — fundamentally changed circumstances.
The distinction matters because the remedies differ. Force majeure, once proven, exempts liability (Article 294) and may extend or end the contract (Article 296). Hardship, under the Civil Code’s changed-circumstances rule, opens a different door: either party may request renegotiation of the contract to restore fairness — and if renegotiation fails, ask the court to adjust or terminate the contract.
So when your partner cries “force majeure” over a price shock, correct the framing in writing: “If you claim impossibility, prove it under the 5-point checklist above. If your real issue is cost, let’s discuss a price-adjustment agreement — that requires our mutual consent, not your unilateral declaration.” This forces them into one of two honest positions: prove impossibility, or negotiate — and bluffing works in neither.
When the force majeure claim is a sham: 4-step response
- Send a reasoned written objection: list each checklist point the partner fails, and demand supplementary evidence within a fixed period (7–15 days). This pressures them and evidences your good faith.
- Demand performance or propose alternatives: e.g., accept late delivery with penalty, or agree a price adjustment for higher costs (if you want to preserve the relationship) — but record it as a new agreement, not an acknowledgment of force majeure.
- Gather evidence of the “real motive”: market input prices at the time, information that the partner sold to a higher-paying third party, reports of their factory operating normally. These demolish the “impossibility” narrative.
- Litigate/arbitrate if needed: demand performance + penalty + damages. The burden of proving force majeure is theirs — when they can’t, they lose.
The special case: when force majeure is real
To be fair, genuine cases exist: a factory inside an absolute lockdown zone, a fully closed port, a sudden embargo. Then:
- You cannot claim damages for the non-performed portion (Article 294).
- But you can require immediate notice (Article 295) and negotiate a deadline extension under Article 296 (up to 5/8 months).
- If extension exceeds the Article 296 limits, both parties may refuse further performance without damages — use the opportunity to renegotiate terms or exit the contract in an orderly way rather than letting the dispute drag on.
FAQ
1. Does COVID-19 still count as force majeure?
It depends on when the contract was signed and the specific facts. For contracts signed from 2022 onward, when the pandemic was widely known risk, invoking COVID-19 as “unforeseeable” is very difficult. For contracts signed in early 2020 amid sudden lockdowns, recognition is more likely. Each case is assessed individually — there is no automatic answer.
2. The Russia-Ukraine war pushed input prices up 40%; the partner wants exemption. Correct?
No. Higher prices, even sharply higher, do not equal impossibility of performance. Force majeure requires inability to perform despite all measures — “performable but at a loss” is a commercial risk the seller bears, unless the contract has a price-adjustment (hardship) clause. Sharing price risk requires renegotiation, not a unilateral force majeure declaration.
3. The partner sent the force majeure notice after 2 months of silence. Can I reject it?
You have strong grounds. Article 295 of the Commercial Law requires immediate written notice; late notice keeps the breaching party liable for damages. Send a written objection citing the notice-duty breach and reserving your damages claim.
4. Who must prove force majeure — me or the partner?
The partner — the party invoking it to escape liability. Article 294 states plainly: “the breaching party has the obligation to prove the exempting circumstances.” You don’t need to prove “no force majeure”; you only need to show what they failed to prove.
5. My contract has no force majeure clause. What then?
It still applies. Force majeure is a statutory exemption ground (Article 294 of the Commercial Law, Article 156 of the Civil Code), independent of whether the contract mentions it. That said, contracts should include the clause to spell out: definition, notice procedure, extension periods, and termination rights — avoiding later arguments.
References
- Civil Code No. 91/2015/QH13: Art. 156.1 (definition of force majeure events) — in force as of 17/10/2026.
- Commercial Law No. 36/2005/QH11: Art. 294 (exemptions), Art. 295 (notice duty), Art. 296 (deadline extension) — in force as of 17/10/2026.
Related articles
- Political Risk Insurance (MIGA, Private): Conditions and Premiums
- Expropriation of Investor Assets in Vietnam: Compensation Standards Under International Law
- Multi-Tier Dispute Clauses (Negotiation-Mediation-Arbitration) in Vietnam: Models and Enforcement
- Waiving Domestic Claims When Filing ISDS Against Vietnam: Scope
- Mediating Investor-State Disputes: Mechanisms and International Experience
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.