Infrastructure promises are contract terms, not marketing talk
When signing a land sub-lease in an industrial park, most companies haggle over rent and skip the technical appendix: substation capacity, water pressure, centralized wastewater plant capacity, completion milestones. Then trial production begins — flickering power ruins a batch, effluent has nowhere compliant to go — and the contract reveals only a vague line about “synchronized infrastructure”.
Legally, every infrastructure commitment written into the contract (including technical appendices and attached working minutes) is a contractual obligation of the lessor. Breach triggers liability under Article 351 of the 2015 Civil Code — unless the breaching party proves force majeure under Article 360.
A four-step claim roadmap, in order
Step 1 — Build the evidence file: log every incident (outage timestamps, measured water pressure), keep copies of remediation requests sent, photograph the treatment plant’s state. Without quantified evidence, every negotiation is weak.
Step 2 — Demand remediation in writing: send an official letter citing the breached clause, set a reasonable cure deadline, and put the lessor on notice of your damages claim.
Step 3 — Negotiate rent reduction / damages: actual losses (spoiled goods, generator fuel costs, late-delivery penalties to your customers) ground a damages claim. Where prolonged infrastructure shortfalls reduce the site’s usable value, a proportional rent reduction is a legitimate demand.
Step 4 — Terminate and sue: where the breach is so serious you cannot achieve the contract’s purpose, consider unilateral termination (if the contract allows) and litigation. This is the last resort — relocating a factory costs far more than persisting with the claim.
Go with fellow tenants or go alone
Park infrastructure is shared — your outage is usually the neighbor’s outage too. A collective petition to the park management board and the infrastructure developer carries far more weight than isolated letters, and shares the cost of consultants and expert assessments. But note: each company still needs its own loss file, because damages are assessed on each party’s actual loss.
Frequently asked questions
The contract only says “synchronized infrastructure” in general terms — can I still claim?
Harder, but not impossible. “Synchronized” is measured against the park’s approved detailed plan and sector technical standards for power, water and environment. Hire a consultant to benchmark actual conditions against the plan/standards as your basis.
Power cuts spoiled my goods — on what basis do I claim?
Article 351 of the 2015 Civil Code: the breaching party must compensate losses, including actual damage and provable lost profit. Keep full documentation: incident minutes, spoiled-goods invoices, remediation costs.
The developer blames “national grid incidents” — is that valid?
Only if they prove force majeure under Article 360 of the Civil Code and show they took all necessary remedial measures. Failures from the park’s own degraded substation are not force majeure.
Can I unilaterally deduct losses from rent?
Not advisable where the contract does not allow set-off — it risks being treated as your own payment breach. Negotiate a written set-off agreement or ask the court/arbitration to decide.
The centralized wastewater plant is unfinished — how do I discharge?
Never discharge sub-standard effluent into the environment — environmental violations are penalized independently of the contract dispute. Require the developer to provide an interim solution (tanker transfer to a compliant facility) at its cost.
Related articles
- Landlord Hikes Rent on Renewal: 3 Negotiation Levers
- Losing Your KCN Land Deposit Over Permit Delays: Can You Recover It?
- 50-Year Lump-Sum Land Lease: 5 Layers of Due Diligence Before Paying
- State Recovers Your FDI Project Land: Compensating On-Land Assets
- Land Recovery Warning Received for Slow Progress: 90-Day Rescue Plan
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.