It is a bitterly common scenario: the project owner has paid the main contractor against accepted progress, the main contractor has the money — and keeps stalling payment to the subcontractor for work the subcontractor has finished. The subcontractor’s instinct is to march to the owner and demand payment, and to receive the cold reply: “we have no contract with you”. Legally, that reply is mostly correct — and understanding why is the first step to collecting through the right door.
The real legal structure: the subcontractor has exactly one direct debtor
Under Clause 27, Article 4 of Bidding Law No. 22/2023/QH15, a subcontractor is an organisation or individual that signs a contract with the contractor to perform work of the package. That definition locks the structure: the subcontract is a two-party relationship between main contractor and subcontractor; the project owner is a third party outside it. Under the privity principle in the 2015 Civil Code, the duty to pay the subcontractor rests on the main contractor — even though the main contractor’s money came from the owner’s progress payment. The owner’s payment to the main contractor creates no direct duty to pay the subcontractor, save three exceptions: a tripartite agreement or written direct-payment arrangement among owner, main contractor and subcontractor; a payment-authorisation or payment-guarantee mechanism set up from the start; and the owner voluntarily confirming substitute liability in writing. Outside these, letters to the owner serve as pressure and quantity confirmation, not as a claim against the right debtor.
Also distinguish lawful subcontracting from prohibited bid transfer: using a subcontractor within the scope and value proposed in the bid or accepted by the owner is lawful; transferring scope beyond that is the prohibited conduct in Clause 8, Article 16 of the 2023 Bidding Law. The distinction matters because a subcontractor whose scope sits inside the lawful subcontracting perimeter stands on far firmer ground when asking the owner and regulators to cooperate on confirmations.
Collecting from the main contractor: a four-rung ladder
Rung one is locking the file: the subcontract and appendices, quantity-acceptance minutes between subcontractor and main contractor (or the owner’s acceptance minutes for the items the subcontractor performed), issued invoices, and a confirmed debt reconciliation. Missing acceptance minutes are the fatal weakness of most subcontractor collection cases, because the main contractor will re-dispute quality and quantities. Rung two is a formal demand letter: amounts by period, the subcontract payment clause relied on, a clear payment deadline, and notice of late-payment interest and any agreed penalty. Rung three is conditional negotiation: accept an instalment schedule only in exchange for an unconditional written debt acknowledgment backed by a personal guarantee of the representative, a mortgage, or a bank guarantee — experience shows oral repayment schedules have no enforcement value. Rung four is suit in the competent court or arbitration under the subcontract’s dispute clause, with interim measures to freeze the main contractor’s receivable at the owner if dissipation is suspected.
Interest and penalties: what else the subcontractor can add
Beyond principal, the subcontractor can claim interest on the overdue sum. Where the subcontract is a commercial relationship, Article 306 of the 2005 Commercial Law allows late-payment interest at the average market overdue rate at the time of payment, unless the parties agreed otherwise. A contractual late-payment penalty follows the agreement but is capped at 8% of the breached obligation’s value under Article 301 of the 2005 Commercial Law. Further proven actual losses — financing costs carried because funds were withheld, storage costs for idle equipment — may be claimed as damages under Article 360 of the 2015 Civil Code. All of these heads should be tabulated separately from the very first demand letter: a large, well-structured total always negotiates better than a round demand.
Using the owner correctly: lawful leverage, not substitute collection
Though not the debtor, the owner is the strongest practical lever when used properly. The subcontractor should notify the owner in writing that the main contractor has been paid for items the subcontractor performed but has not paid onward, asking the owner to confirm accepted quantities and, in later payment periods, to consider a direct-payment mechanism or retention of the corresponding amount where the main contract and the law allow and the main contractor consents in writing. For state-funded packages, the subcontractor may also petition the bidding authorities about the main contractor’s conduct where its default towards subcontractors affects the package. One boundary to keep: do not withhold as-built documents, obstruct others’ work, or publish unverified accusations — those moves can turn the collector into the breaching party.
Frequently Asked Questions
The main contractor was paid but the subcontractor was not — who owes the money?
The main contractor — the sole direct debtor under the subcontract, on the basis of Clause 27, Article 4 of the 2023 Bidding Law defining a subcontractor as a party contracting with the contractor. The project owner owes no direct payment duty unless there is a tripartite agreement, a direct-payment mechanism, or a written substitute-liability confirmation.
Where does a subcontractor sue the main contractor for payment?
Where the subcontract’s dispute clause points: the competent People’s Court, or commercial arbitration if agreed. Where the main contractor shows signs of dissipating assets, seek interim measures freezing its receivable at the project owner in parallel with the suit.
Can the subcontractor charge interest and late-payment penalties?
Yes. For commercial relationships, Article 306 of the 2005 Commercial Law gives late-payment interest at the average market overdue rate unless otherwise agreed. A contractual penalty follows the agreement but is capped at 8% of the breached value under Article 301; other proven losses are recoverable under Article 360 of the 2015 Civil Code.
Can the project owner pay the subcontractor directly instead?
Only on a written basis: a tripartite agreement, a direct-payment mechanism established from the start, or the main contractor’s written authorisation for the owner to retain and pay directly. Otherwise the owner’s proper role is confirming accepted quantities and pressuring the main contractor to perform.
Related articles
- After Getting IRC/ERC in Nghe An: 10 Immediate Follow-Up Steps (Tax, Invoicing, Labor, Banking)
- After Getting IRC/ERC in Vinh Phuc: 10 Immediate Follow-Up Steps (Tax, Invoicing, Labor, Banking)
- After Getting IRC/ERC in Ba Ria-Vung Tau: 10 Immediate Follow-Up Steps (Tax, Invoicing, Labor, Banking)
- Actual Timelines at the Department of Planning and Investment: Statutory Days vs Reality, and Where Delays Happen
- Actual Timelines at the Industrial Park Management Board: Statutory Days vs Reality, and Where Delays Happen
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.