Foreign Investment

Leasing Land for Mining: Term and Land Rental

Low-angle shot of trees

The mining land lease term is locked by two clocks

Land used for mineral activities belongs to the leased-land group under Land Law No. 31/2024/QH15: economic organisations, including foreign-invested enterprises, are leased land by the State to implement a mineral mining project. The lease term is locked by two factors at once. The first is the land use term for an investment project under Article 172 of the 2024 Land Law — not more than 50 years, and in special cases not more than 70 years — tied to the investment project’s operating term. The second, decisive in practice, is the term of the mining licence and the licensed reserves under Geology and Minerals Law No. 54/2024/QH15: a mining licence issues against approved reserves and a mining plan, so mining land is in practice leased for a term matching the mine life, extendable when the mining licence is extended or reissued as prescribed.

A point enterprises often miss: mining land rent covers two area layers of different character — the pit area and works serving mining (waste dumps, beneficiation workshops, internal roads, mine offices) inside the project boundary are leased; while deep processing items and a refinery placed outside the mine boundary follow the ordinary industrial project land lease regime. Mixing the two layers in one land lease file slows the whole process and distorts rent calculation by land use purpose.

How mining land rent is calculated

Land rent for a mining project is determined under the current land framework: the rental unit price is a percentage of the land price for rent calculation under the local land price table and adjustment coefficient for the corresponding use purpose, multiplied by the leased area and adjusted by lease form — annual payment, or one-off payment for the whole term where that choice is available. Land for mineral activities is in many cases leasable only on annual payment given its special use character, and the unit price is stabilised for the rent stabilisation cycles land law prescribes, then adjusted to land prices at the adjustment point.

Beyond rent, a mining project’s total land cost also includes: compensation and support amounts when the State recovers land from current users for the project under the approved plan (in the recovery-based leasing mechanism, the project advances compensation and site clearance funds); the mineral mining right fee — a separate minerals law charge calculated on reserves, not land rent though often merged in financial models; and mine closure obligations including the cost of rehabilitating the mined area’s environment and land. The investor should have advisers split these four items into four independent model lines, because each has a different calculation basis and collecting authority.

When the mining licence expires or the mine closes early: where the land goes

When the lease term ends or the mining licence terminates, the enterprise must perform the mine closure chain under geology and minerals law and the corresponding land duties: complete the mine closure plan, rehabilitate the environment and land of the mined area to a state inspected and confirmed by the competent authority; hand the land back to the State as prescribed and handle land-attached assets under the approved plan. Land rent ends only when the handover completes — stopping mining without finishing rehabilitation and handover leaves the land lease relationship and its related duties still under management effect.

Where the project obtains a mining licence extension or a boundary expansion, land leasing adjusts correspondingly: extend the lease term for the existing area and lease additionally for the expanded area with updated land dossiers. Conversely, a project whose mining licence is revoked for violations faces land recovery under the Land Law 2024 recovery cases at the same time, with invested cost handling following the principle that the violation rests with the violating party — a scenario to price into due diligence when acquiring an operating mine project.

Frequently asked questions

What is the maximum lease term for mining land?

The general frame under clause 1 of Article 172 of Land Law 31/2024/QH15 is an investment project term of not more than 50 years, and not more than 70 years in special cases. For mining land, the actual term tracks the mining licence term and licensed reserves under Geology and Minerals Law 54/2024/QH15, and extends correspondingly when the mining licence is extended.

How is mining land rent calculated?

Under the current land frame: the rental unit price is a percentage of the rent-calculation land price (the local land price table and adjustment coefficient for the corresponding purpose) times the leased area, by annual or one-off payment form where choosable; the unit price is stabilised for statutory cycles then adjusted. This is separate from the mineral mining right fee calculated on reserves.

What happens to the land when the mining licence expires?

The enterprise must carry out mine closure, rehabilitate the environment and land until inspected and confirmed, then hand the land back to the State; land-attached assets are handled under the approved plan. The lease relationship and related duties close only when handover completes — merely stopping mining does not itself end the land duties.

Related articles

Reviewed by the Legal Practice Group – FLAT LAW FIRM

This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.