The direct power purchase mechanism, or DPPA, is the largest structural change in Vietnam’s power market in years, because for the first time large electricity consumers can buy renewable power directly from generators instead of only from the grid through EVN. For an FDI factory carrying group renewable commitments and export market mechanisms, DPPA is the main instrument turning that commitment into an actual contract.
Two DPPA models: private line and through the grid
The DPPA frame, established by Decree 80/2024/ND-CP and carried into Electricity Law 61/2024/QH15, has two models. The private line model lets a renewable seller invest in a dedicated transmission line straight to a large electricity customer, with price and conditions freely agreed between the two sides in a direct power purchase agreement outside the power market price mechanism.
The grid model works as a financial contract for difference: the seller sells power into the power market, the customer keeps buying physical power from the grid as usual, and the two sides settle the difference between the agreed contract price and the market price on recorded renewable output. This model needs no private line and suits a factory anywhere on the grid, in exchange for which the customer still bears the full grid, transmission and dispatch charges in its ordinary power bill.
Who may participate and what the contract contains
Sellers are renewable plants such as solar and wind farms meeting the mechanism’s conditions; buyers are large electricity customers reaching the consumption threshold and connection voltage under the competitive wholesale market rules issued by the Ministry of Industry and Trade. An FDI factory wishing to join must compare its average consumption against the current large customer threshold and complete participation registration with the power market operator.
A standard DPPA contract must lock: committed volume and how renewable output is recorded, the contract price and its adjustment mechanism over time, a term typically spanning many years to match the power project’s life, allocation of volume and market price difference risk in the grid model, the renewable energy certificates accompanying output, and termination or assignment conditions where the factory changes owner or relocates. Renewable certificates are the point export factories must verify carefully, because they are the evidence for declaring renewable use to buyers and carbon mechanisms.
Practical differences between DPPA and rooftop solar
DPPA and self-consumption rooftop solar solve two different needs. Rooftop solar is limited to the factory roof’s scale in a self-use model with capped surplus sales, while DPPA lets a factory buy renewable volume at large scale from solar or wind projects far away, by private line or through the grid. Many FDI factories combine both: rooftop for daytime base load and DPPA for the remaining volume to reach a target renewable share.
The risk to manage in a DPPA lies in the contract’s long term: a fixed or formula-anchored contract price while market prices move, actual renewable output depending on weather in the grid model, and policy adjustments to grid use charges. DPPA negotiation is therefore a joint legal and financial exercise, requiring market price scenario modelling before locking a long term.
Frequently Asked Questions
Which model should an FDI enterprise choose: direct private line or grid-based CfD DPPA?
The choice depends on the factory’s location and consumption profile. The private line model suits a factory with large, stable load within feasible distance of a renewable project, where the sides are ready to invest in a dedicated transmission line. The grid model suits a factory far from renewable sources or wanting fast deployment without transmission investment, in exchange for living with the market price difference mechanism. Many FDI factories start with the grid model to reach a renewable share early, then assess a private line once consumption scale is large enough.
How do the two models differ?
The core difference lies in the physical power flow and the money flow. In the private line model, power runs straight from the renewable plant to the consuming factory over a line the sides invest in, and the price is agreed all-in between them outside the market mechanism. In the grid model, the factory keeps buying physical power from the grid as usual, the seller sells power into the power market, and the two sides settle only the difference between the contract price and the market price on recorded renewable output.
Which is cheaper and which is more stable?
There is no absolute answer on either criterion. On cost, the private line avoids most grid use charges and gives an agreed price that is predictable over a long term, but requires line investment capital and private line operating cost; the grid model needs no line capital but total cost moves with power market prices and grid fee policy. On stability, the factory’s physical supply in both models rests on the national grid to differing degrees; the largest stability difference lies in price, where the private line is usually steadier and easier to model.
What are the participation conditions for each model?
Common conditions for both models: the seller is a renewable project meeting DPPA mechanism conditions, the buyer is a large electricity customer reaching the consumption threshold and connection voltage under competitive wholesale market rules. The private line model additionally needs agreement and investment on the transmission line and connection point between the power plant and the customer. The grid model additionally needs participation registration with the power market operator and metering and output recording systems for difference settlement.
Bottom line for factories weighing a DPPA
DPPA opens a real-scale renewable purchasing channel for FDI factories, through private line and grid models with different price logic. The signing decision should rest on scenario modelling of prices and volumes across the contract’s long term, plus verification of renewable certificates, rather than on the first-year contract price alone.
Related articles
- Converting Paddy and Forest Land Use Purposes for Projects After Mergers: Decision Authority of the New Provinces
- Foreigners' Home Ownership in Vietnam After the 2023 Housing Law: The 30% Cap per Building and the 50-Year Term
- Social Housing for Industrial Park Workers Self-Invested by FDI Enterprises on Leased Land: Conditions and Leasing Rights
- The 20% Land Fund in Commercial Housing Projects for Social Housing: Paying Money Instead and the New Calculation Method
- Incentives for Social Housing Developers: Land-Use Fee Exemption, Taxes and the 10% Norm Profit — Conditions and Post-Project Inspection
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.