Real Estate and Construction

Converting Paddy and Forest Land Use Purposes for Projects After Mergers: Decision Authority of the New Provinces

Scenic aerial photograph of vibrant rice fields in Kon Tum, Vietnam, showcasing stunning agricultural landscapes.

A provincial merger changes more than the name on a map. For a project that must convert paddy land or forest land to another purpose, the merger changes the deciding authority itself: a resolution of the new province’s People’s Council becomes the threshold condition under clause 1 of Article 122 of the 2024 Land Law, and the district level — which used to handle part of the file — no longer exists in the two-tier local government.

Legal basis

  • Article 116 of Land Law No. 31/2024/QH15: the bases for land allocation, land lease and permission to change land-use purpose include the approved annual land-use plan, the land-use demand stated in the investment project and the locality’s land fund capacity.
  • Clause 1, Article 122 of Land Law No. 31/2024/QH15: the competent authority may decide on land allocation, land lease or permission to change the use purpose of paddy land, special-use forest land, protection forest land and production forest land only after a resolution of the provincial People’s Council, except for projects whose investment policy is approved or decided by the National Assembly or the Prime Minister under the laws on investment, public investment, PPP or petroleum, or approved by the provincial People’s Council itself under the public investment or PPP laws.
  • Article 123 of Land Law No. 31/2024/QH15 on authority: the provincial People’s Committee decides allocation, lease and change of use purpose for organisations; the commune-level People’s Committee decides for individuals.
  • Decree No. 102/2024/ND-CP guiding the Land Law: detailed criteria, conditions and procedures for converting paddy and forest land; Decree No. 112/2024/ND-CP on paddy land management and use prescribes the payment a land user must make so the State can supplement the paddy area lost to conversion.
  • Resolution No. 202/2025/QH15 on the arrangement of provincial administrative units: from 1 July 2025 Vietnam has 34 provincial-level units and a two-tier local government without the district level.

After the merger, who decides?

The answer has two layers. The condition layer: converting paddy or forest land first requires a resolution of the provincial People’s Council — after a merger, the Council of the newly formed province, the only body entitled to vote on converting these sensitive land groups within the province. The decision layer: the new province’s People’s Committee issues the administrative decision permitting the change of use purpose for organisations and project enterprises, while the commune-level People’s Committee handles individual cases. Files no longer pass through a district level, but that does not make the procedure lighter: appraisal of land-use demand and checking against the paddy and forest conversion quotas allocated to the province now concentrate in the new province’s specialised departments, over a wider territory than before.

The sole exception to the People’s Council resolution condition covers projects whose investment policy belongs to the National Assembly or the Prime Minister under the investment laws, and projects whose policy the provincial People’s Council approves itself under the public investment or PPP laws. An investor must pin down this exception correctly at the filing stage, because choosing the wrong track renders the conversion decision one issued without its threshold condition.

Converting paddy land: quotas, the resolution and the paddy protection payment

Paddy land is the most strictly protected land group. Beyond the provincial People’s Council resolution, conversion must fit within the paddy conversion quota allocated to the province under national land-use planning; once the quota is exhausted, no provincial resolution can legitimise further conversion. The party allocated, leased or permitted to convert the land must also pay a sum for the State to supplement the lost paddy area or raise paddy land efficiency under Decree No. 112/2024/ND-CP, at a rate set by the provincial People’s Committee within the Government’s framework. This payment is a real project cost that belongs in the total investment estimate from day one, so the obligation does not surface as an unbudgeted surprise after approval.

Forest land: conversion depends on forest type and replacement planting

For forest land, the 2024 Land Law places special-use, protection and production forest land in the same group requiring a provincial People’s Council resolution for conversion, but forestry law adds its own layer of conditions. Changing forest use purposes must conform to national forestry planning and provincial planning, proceeds only with a project whose conversion policy is decided by the competent authority, and as a general principle conversion of natural forest is restricted to the maximum. The converting party must plant replacement forest of equivalent area or pay a replacement-planting sum into the Forest Protection and Development Fund under Forestry Law No. 16/2017/QH14. For special-use forest, apart from narrow cases serving national defence, security or urgent projects decided by the Prime Minister, the door to commercial conversion is nearly closed — a point investors must check before including a forest plot in a project plan.

How does converted land reach the project?

A change of use purpose only unlocks the land-planning layer; the project then accesses land through the allocation and lease channels of the 2024 Land Law, among which land-use-right auction is mandatory for many state-managed land funds, including the online auction format provinces are rolling out on the National Asset Auction Portal. Deposit conditions, forfeiture and post-winning obligations are set by Articles 55 to 58 of Decree No. 102/2024/ND-CP — the subject of the questions below.

Conclusion and recommendations

After the mergers, authority over paddy and forest land conversion concentrates in the new province at both layers: the new People’s Council sets the condition by resolution, and the new People’s Committee issues the administrative decision for organisations. An investor planning a project on paddy or forest land should do three things early: reconcile the province’s remaining conversion quota, determine whether the project falls under the central-level investment policy exception, and fully budget the paddy protection payment and replacement-planting costs in the initial financial model.

Frequently asked questions

What deposit ratio applies in online land-use-right auctions and through which channel is it paid?

For organisations bidding for land-use rights, point c, clause 1, Article 55 of Decree No. 102/2024/ND-CP sets the deposit at 20% of the total value of the land plot or land area calculated at the starting price; individuals are governed by clause 4 of Article 125 of the 2024 Land Law and the corresponding decree conditions. The deposit is paid by bank transfer to the account of the designated auction organisation or professional auction practice organisation; for online sessions it is paid through the payment gateway integrated in the online auction system and the National Asset Auction Portal. Participants must complete payment and registration before the application closing time stated in the auction notice; late payment means the participant is treated as ineligible.

In which cases is the deposit refunded, and in which cases is it forfeited?

Deposits are refunded to unsuccessful bidders, to winning bidders who have fulfilled their financial obligations under the contract, and to all participants where the auction fails or is cancelled because of a technical fault or a competent authority’s decision; refunds follow the time limit in the Law on Asset Auctions and the auction rules, normally within three working days from the auction’s closing date. Conversely, a winning bidder who rejects the result, fails to sign the auctioned-asset sale contract or fails to pay the winning amount within the notified deadline forfeits the deposit to the state budget, the result is cancelled under Articles 55 to 58 of Decree No. 102/2024/ND-CP, and the land is put up for auction again.

How is the result handled when an online auction session suffers a technical fault?

The Law on Asset Auctions, as amended by Law No. 37/2024/QH15, provides a dedicated regime for online auctions: the auction runs on a system that logs every bidding action, and the auction rules must anticipate technical incidents in advance. When a system fault interrupts bidding or undermines fairness, the professional auction organisation must suspend the session, minute the incident, notify participants and the competent authority; a seriously faulted session is cancelled and re-run from the start, with deposits refunded in full. A result is only reviewed for cancellation where a complaint or denunciation shows the technical fault actually distorted the bidding outcome; participants should keep their electronic receipts and bidding logs for reconciliation if needed.

Within what time limit must a winning bidder sign the contract and pay after an online session?

Once the winning result is approved by the competent People’s Committee, the auction organisation issues a winning notice and the winner must sign the auctioned-asset sale contract with the unit assigned to organise the auction, normally within five working days from receipt of the notice under the forms in Decree No. 102/2024/ND-CP. The winning amount is paid in a lump sum or in instalments as set in the approved auction plan; for investment projects, deadlines for land-use levy and land rent follow the tax authority’s notice issued after the land allocation or lease decision. Missing the payment deadline without an accepted reason leads to cancellation of the result, forfeiture of the deposit, and possible restrictions on joining later auctions in the locality.

Related articles

Reviewed by the Legal Practice Group – FLAT LAW FIRM

This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.