What as-built completion means in current legal language
As-built completion is not a standalone licence but the closing chain of the construction phase: completion acceptance putting the works into use under construction quality management law, as-built drawings recording exactly what was built, and — for the certification goal FDI investors care about — registration of ownership of assets attached to land. For an FDI enterprise leasing land, assets on the land belong to the enterprise and are recorded in the certificate of land use rights and ownership of land-attached assets issued to the land lessee under Land Law No. 31/2024/QH15 and Decree 101/2024/ND-CP on land registration and certification.
Separate the two steps clearly: completion acceptance is a matter between the investor and the construction participants and, for projects subject to acceptance inspection, involves the construction authority’s check; certification is a registration procedure at the Land Registration Office. They connect: asset registration must rest on a project that has passed completion acceptance with valid as-built drawings. A project without completion acceptance has no basis for registering asset ownership.
The completion dossier and the asset registration dossier in practice
The project completion file the investor must assemble and archive includes: the appraised, approved design and in-construction design adjustments; as-built drawings confirmed by the contractor and supervision consultant; acceptance minutes for each work part and phase and the completion acceptance minutes; test and verification results for technical systems including fire protection under the current self-acceptance regime, electrical and water systems; and the project legal file including the construction permit and its amendments. For asset certification, the dossier filed at the Land Registration Office comprises the standard-form registration application, land documents (land lease contract, issued certificate), the construction permit, as-built drawings or a current-status survey of the asset as the registration authority requires, and related financial obligation receipts.
Certification timing after a valid dossier follows the land registration time limits in Decree 101/2024/ND-CP — first registration and asset change registration are conventionally measured in working days from receipt of a complete valid dossier, but the enterprise’s real total time is usually stretched at the earlier stage: finalising acceptance minutes, closing fire findings and re-surveying where the status quo deviates from drawings. Financial planning should count title timing from the completion acceptance milestone plus a margin for registration supplementation, not from the registration filing date alone.
Partial deviation and no completion: two situations handled differently
Where part of the works deviates from the permit and approved design, that part must be resolved before its completion acceptance: if the deviation is of a type eligible for permit and design amendment, amend first and accept on the amended basis; if it is a violation not eligible for amendment, demolish and restore to design before acceptance. Completion acceptance for the conforming parts can still proceed by phase or independent item under quality management rules, letting the plant bring valid sections into operation while the deviation is resolved — provided the operating boundary of the section put into use, especially its fire safety, is independently assured.
Skipping completion — not organising completion acceptance and not registering the asset — is not fined as a standalone act merely for being late, but the knock-on consequences are heavy: the asset cannot be certificated so it cannot be mortgaged at a bank, is hard to fully book and insure, a project transfer or factory sale buyer will demand completion as a condition precedent, and if the physical works contain construction violations, time passing does not erase them — authorities can still inspect, fine and order remediation on discovery. For an FDI investor planning exit or restructuring, completion and certification belong on the mandatory work list during plant operation, not deferred until transaction time.
Frequently asked questions
What documents are needed for factory as-built completion?
Two file layers: the project completion file (approved design and adjustments, as-built drawings confirmed by contractor and supervisor, phase and completion acceptance minutes, system test results including fire protection, construction permit) and the asset registration file at the Land Registration Office (standard-form application, land lease documents, construction permit, as-built drawings or status survey, financial receipts).
How long does title issuance take?
The Land Registration Office stage follows the procedural time limits in Decree 101/2024/ND-CP from a valid dossier. The enterprise’s real timeline is usually longer because it sits in finalising acceptance, closing fire findings and surveying the status quo; plan title timing from the completion acceptance milestone plus a supplementation margin, not from the filing date alone.
Can a partly non-conforming build be completed?
The conforming parts can be accepted and registered by phase or independent item. The deviating part must be resolved first: amend the permit and design if the deviation is eligible for amendment, or demolish and restore if it is not. An unresolved deviating part cannot pass completion acceptance and cannot be recorded in the certificate.
Is there a fine for not doing as-built completion?
Lateness alone is not a separately fined act, but without completion acceptance the asset cannot be registered or certificated for mortgage or a clean transfer. If the works in fact contain unpermitted or non-conforming construction, the violation can still be inspected, fined and ordered remedied on discovery even after years of operation.
Related articles
- Foreign law firm offices in Vietnam: establishment conditions
- Petroleum trading by foreign investors: is it permitted?
- Foreign-invested pharmacy retail chains: permitted?
- Franchising into Vietnam: conditions and registration
- Exporting to the US from Vietnam: rules of origin and circumvention investigation risks
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.