Construction Delay Disputes in Vietnam: 8% Penalties, Damages and Extensions

Workers Laying Out Concrete Reinforcements at the Construction Site.

The 8% figure is the most misunderstood number in construction delay disputes: it caps the agreed penalty, calculated on the breached portion of the contract — not 8% of the whole contract value, and not automatically the employer’s entire loss. This article separates the three layers of money the parties habitually merge into one.

Legal basis

  • Law on Construction 50/2014/QH13 (amended by Law 62/2020/QH14)
  • Decree 37/2015/ND-CP on construction contracts (amended by Decree 50/2021/ND-CP)
  • Civil Code 91/2015/QH13

The 8% penalty: cap, base and conditions

Under the construction-contract framework (Decree 37/2015/ND-CP on construction contracts), the breach penalty is as agreed in the contract but may not exceed 8% of the value of the breached contract portion. Three decisive points: the “breached portion” is the delayed work (items/stages late), not the whole project; the penalty is an agreed sanction — the employer need not prove loss to claim it, but must prove the breach (delay against the contract programme) and that a penalty was agreed; and if the contract is silent on delay penalties, the employer cannot imply one and must go the damages route.

Damages: the second layer, on entirely different conditions

Beyond the penalty, the employer may claim actual loss from the delay: extended supervision costs, loan interest, loss from late commissioning, and sums owed to third parties (committed buyers/tenants). Unlike the penalty, damages require full proof of loss, causation and fault under the Civil Code 91/2015/QH13. Read the contract closely: many construction contracts make the penalty the sole remedy for delay, or set an aggregate liability cap covering both layers — the drafting and interpretation of those clauses decide most of the dispute.

The contractor’s defence: extension of time (EOT)

The contractor is not penalised for delay caused by: force majeure, employer-ordered design/scope changes, late site handover or late payment by the employer, and other objective causes under the contract. The condition is procedural: the contractor must notify the event and claim the extension within the contract’s time limits, with a critical-path impact analysis. Delay cases are won on site records (construction diaries, progress-meeting minutes, delay warnings) rather than hearing advocacy — the side with the better records usually wins.

Related reading on flaw.vn: article EXP-1784 covers the general framework of this topic — this article deals only with the specific angle in its title.

Frequently asked questions

How much is the penalty for delay?

The penalty equals the contract’s agreed rate multiplied by the value of the breached portion (the delayed work), capped at 8% of that portion under the construction-contract framework in Decree 37/2015/ND-CP — not 8% of the entire contract value. The employer need not prove loss for the penalty, but must have an agreed penalty clause and prove the delay.

In which cases can an extension be granted?

Possibly, if the contract does not exclude it. Beyond the penalty, the employer may claim proven actual loss (extended costs, late-commissioning loss, third-party liabilities) under the Civil Code 91/2015/QH13. But many contracts make the penalty the sole remedy for delay or set an overall liability cap — read the specific contract before adding the two layers.

Compensation for damages caused by delay (storage, loan interest)?

The contractor earns an extension where delay stems from causes not its fault under the contract: force majeure, employer design/scope changes, late site handover, late payment. The survival condition is notifying and claiming the extension within the contract’s deadlines, with critical-path impact analysis — skipping the procedure usually defeats the claim even where the reason is sound.

What if delay is caused by both parties?

Both sides win on site records: the approved detailed programme as the baseline, construction diaries and weekly progress minutes, notices of delay events and extension claims, and stage-by-stage confirmations of delay causes. These records decide how delay days are allocated between the parties — the centre of every delay dispute.

Related articles

Reviewed by the Legal Practice Group – FLAT LAW FIRM

This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.