Design Changes During Construction: Minor Changes vs Changes Requiring Re-approval

Low-angle shot of crane under blue sky

The dividing principle: does the change alter what was approved?

Vietnamese construction law does not define a minor change by a materials list but by impact: under Construction Law No. 50/2014/QH13 (amended by Law No. 62/2020/QH14) and the decree on construction investment project management, the appraised and approved construction design is the legal basis for building; during construction the investor may decide design adjustments that do not change scale, function, the main structural solution, load-bearing safety, fire safety or other content appraised by the specialised authority. Any adjustment crossing that line must have the changed part re-appraised before the related work is built.

Three quick filter questions for the site engineer. One: does the change touch load-bearing structure, imposed loads or the foundation solution — if yes, it is never minor. Two: does it touch fire protection — position or size of escape routes, fire compartments, fire-proofing materials, alarm and suppression systems — if yes, the fire part must be re-appraised under fire law before construction. Three: does it change construction permit indicators — density, height, floor count, building footprint — if yes, the construction permit must be amended. Only when all three answers are no does the change fall into the investor-decided minor group.

The boundary on situations FDI factories meet most

Swapping finishing materials — tiles, paint, ceilings, lightweight non-load-bearing partitions that are not fire-rated elements of the design — is usually minor provided it does not materially change loads or breach material requirements in the appraised file. Swapping fire door types, fire partitions or intumescent paint on steelwork, by contrast, is a fire change even though it looks like a materials swap: the replacement’s fire certification must be equivalent and the changed part must go through fire re-appraisal. Moving machinery inside the plant is minor in construction terms but can become major for fire and environment if it changes fire load, safety distances to chemical stores or escape routes — the point where FDI process teams and construction teams most often assess differently.

Changes increasing floor area, adding a load-bearing mezzanine, converting an area from production to dangerous goods storage, or altering the wastewater solution beyond the boundary covered by the environmental impact assessment all belong to the group needing rework at the corresponding licence layer — construction, fire or environment — and cannot be regularised by a site minute. Conversely, relocating an internal door not on an escape route, or adjusting floor levels within a range not affecting drainage and structure, is normally decided by the investor and recorded in the as-built file.

Procedure for each group and sanctions for choosing wrong

For a minor change: the investor or its authorised person decides in writing, the design firm confirms conformity, the contractor builds to the adjusted design, and everything is reflected in the as-built drawings. No resubmission to the appraisal authority is needed, but the adjustment decision file must be kept with the construction quality management file for acceptance and inspection. For a change needing re-appraisal: the sequence is design the changed part, re-appraise the changed part (construction and fire, by content touched), amend the construction permit if permit indicators change, and only then build the changed part. Building first and applying later is a construction-order violation.

Sanctions for building contrary to the appraised and approved design or the construction permit include fines under the current construction administrative penalty decree, remedial measures, demolition of the violating part, or permit amendment where conditions allow. Unauthorised fire design changes are additionally handled under fire law. On who decides the character of a change: the law gives the investor the right to decide minor adjustments on the design firm’s professional assessment, but the final word in a dispute belongs to the State construction management and appraisal authorities at inspection and acceptance — so for a change sitting on the boundary, the wise move is to seek the licensing or appraisal authority’s written opinion before building and keep the reply as protective evidence.

Frequently asked questions

Does changing finishing materials require re-approval?

Usually not, if the replacement is non-load-bearing, is not a fire-rated element of the fire design, and does not materially change loads or function — the investor decides in writing with the design firm’s confirmation and records it in the as-built file. Changing fire doors, partitions or fire paint is a fire change and needs fire re-appraisal of that part.

Which changes mandatorily require re-appraisal?

Changes altering main scale or function; the load-bearing structural or foundation solution; the fire solution (escape, compartments, alarm and suppression systems); or construction permit indicators such as height, floor count and density. These must have the changed part re-appraised and related permits amended before that part is built.

How much is the fine for unauthorised design changes?

Fines are set by act and project scale in the current construction administrative penalty decree, with remedies such as demolition of the unpermitted part or compulsory permit amendment where conditions allow. Fire-related changes are additionally handled under fire law. The bigger risk than the fine is that wrongly built parts fail acceptance and cannot be certificated as assets.

Who decides whether a change is minor or major?

The investor decides adjustments at project level, on the design firm’s professional assessment — that is the mechanism construction law provides. But where the management or appraisal authority concludes at inspection or acceptance that the change needed re-appraisal, the State conclusion prevails; boundary changes should be cleared by written opinion of the competent authority before building.