Scenario: an FDI project receives a suspension notice for alleged slow progress and breach of investment conditions. The board panics: “How long until the project is terminated? What rights do we still have?” Project suspension is a serious administrative measure but not a death sentence — it is a decision that can be complained against, sued over and, most importantly, lifted if the company follows the right sequence and fixes the exact “bottleneck” the authority cited. This article maps the route when an FDI project is suspended under the Law on Investment 143/2025 framework.
What is project suspension, and how does it differ from termination?
Under the Law on Investment 143/2025 (replacing Law 61/2020 from 1 March 2026), the investment registry authority may suspend a project’s operation in statutory cases — typically where the project must pause to remedy land, environmental or construction violations, or where the investor fails operating conditions. Suspension is a temporary, liftable measure: operations halt during remediation while the investment certificate survives.
Project termination is the far heavier step: the project ends its legal life, triggering land, asset and financial-obligation handling — arising where the investor decides to terminate, the term expires unextended, land is recovered, or a suspended project fails to remedy within the set period. The company’s life-or-death line sits exactly here: whether “liftable suspension” hardens into “permanent termination” depends on conduct during the suspension.
The investor’s rights and action route
- Read the suspension instrument properly: legal basis, the specific violation, duration and lifting conditions — a vague basis is the first weakness to attack in a complaint;
- Administrative complaint: complain against the administrative decision under the Law on Complaints to its issuer or direct superior, within the complaint limitation — while filing a remediation plan with a roadmap and evidence of started implementation;
- Administrative lawsuit: if the complaint fails, sue the suspension decision in court under the Law on Administrative Procedures, with interim-relief requests where suspension causes irreparable harm;
- Parallel technical work: most suspensions are lifted at the technical table — remedying the exact cited violation (progress, environment, land) with specialist-authority confirmation — rather than in the courtroom.
How long until suspension becomes termination — and how to prevent it
There is no single “automatic termination” day-count for all projects: duration and consequences are set by the suspension instrument and the legal basis of the specific case — sometimes tied to an authority-set remediation deadline, sometimes to land recovery under land law. The fatal mistake is “lying still until suspension lapses”: silence during suspension both drains the complaint limitation and builds a “failure to remedy” record for the termination decision that follows. The right strategy runs three tracks at once: protect limitation (complain/sue on time), remedy for real (milestoned, confirmed), and build the good-faith record (archive every letter both ways) so that if the matter escalates into a larger dispute — including an international investment dispute — page one of the file already exists.
Frequently asked questions
What should I do when my FDI project is suspended?
Four immediate steps: read the suspension instrument closely (basis, violation, duration, lifting conditions); file an administrative complaint in time with a remediation plan; consider an administrative lawsuit with interim relief; and technically remedy the cited violation to obtain lifting confirmation.
What rights does the investor have when suspended?
The right to know the basis and reasons; to complain against the administrative decision under the Law on Complaints; to sue in administrative court under the Law on Administrative Procedures; and to have the suspension lifted once the violation is remedied per the instrument’s conditions.
How long can suspension last before revocation?
There is no common day-count: duration and consequences follow the suspension instrument and the case’s legal basis — usually tied to a set remediation deadline. Termination risk arrives when remediation fails within the deadline or land is recovered under land law.
How do I get the suspension lifted?
Remedy the cited violation fully, obtain the specialist authority’s confirmation, file the lifting request with remediation evidence, and keep the complaint in time to maintain legal pressure. Never lie still — silence builds a “no remediation” record.