Short answer: There is no statutory fixed figure for early termination — the colocation contract sets it, within the commercial sanction limits the law allows. Customer data, by contrast, follows a clear principle: the data sits under the customer’s control, and a provider may not turn it into a hostage for unpaid invoices, even where the debt is real.

Termination fees: read the contract first, then the cap

A colocation agreement is a commercial contract; when a customer leaves early, financial consequences are those agreed — termination charges computed on remaining months, breach penalties and proven actual loss. Under the sanction framework of the Commercial Law 36/2005/QH11, an agreed penalty may not exceed 8% of the value of the breached obligation portion; damages beyond penalty must rest on proven actual loss. Providers often miss one point: if the contract contains no early-exit clause, the customer does not automatically owe an industry-custom fee — every sum must trace back to a signed clause or proven loss. Conversely, a customer cannot ignore an agreed notice period simply because a new provider is ready.

Data at exit: who holds, who deletes, by when

Under the Personal Data Protection Law 91/2025/QH15 (effective 01/01/2026) and Decree 356/2025/ND-CP, a data center acting as processor handles data on the instructions of the customer as controller; when the service ends, the default duty is to return and delete data as instructed, save for portions sector law requires to be retained. Retaining the full dataset to pressure payment puts the provider in breach of its data protection duties — quite apart from liability if the data leaks while held against the agreement. The correct structure separates the two relationships: invoice debt is pursued with contract and civil-law tools (deposit set-off where agreed, litigation, arbitration), while data follows a handover path — migration window, delivery format, deletion confirmation — set out in a termination schedule.

Draft the exit on day one

  • Express termination charges as a formula over remaining months, not an ungrounded lump sum.
  • Fix a post-termination migration window for data and equipment, with storage fees if the customer overstays.
  • Require written deletion confirmation once handover completes.
  • Keep deposit and payment-security clauses separate from data-handling clauses.

Frequently asked questions

How much does early termination of a server colocation lease cost?

Whatever the signed contract provides: typically a charge over the remaining term, a breach penalty (capped at 8% of the breached obligation’s value under the Commercial Law) and proven actual loss. With no early-exit clause, the provider cannot impose a customary fee and must rely on proven loss.

Who has the right to hold data on the servers when the contract ends?

The customer, as data controller, decides on return or deletion. The data center, as processor, retains only data that sector law compels it to keep, and must delete the rest on instruction after service ends, with written confirmation.

Can a data center retain customer data to collect unpaid fees?

It should not, and in principle may not: holding a customer’s data as collection leverage conflicts with processor duties under Law 91/2025 and Decree 356/2025. Fees must be collected through contract tools — agreed deposit set-off, payment demands, arbitration or court — not through data.


Related articles

Reviewed by the Legal Practice Group – FLAT LAW FIRM