Scenario: during a routine dossier review, the environmental manager discovers the plant’s environmental permit expired four months ago. The renewal application was “being prepared” but never filed; production never stopped. The director’s first reaction: keep quiet, file now, hope no inspection lands in between. The second reaction — the right one — is to understand that every day of operation without a valid permit is a separate, accumulating liability.
An expired permit equals no permit
The 2020 Law on Environmental Protection is unambiguous: facilities that must hold an environmental permit may only discharge waste and operate with a valid permit (Articles 39–49). An expired permit has no legal effect — operating on it is legally identical to operating without a permit. Article 40(4) sets the validity: 7 years for group-I investment projects (and pre-2022 facilities with group-I-equivalent environmental criteria), 10 years for the rest.
The practical consequence: the plant is now in the sanction frame for “operating without an environmental permit” under Decree 45/2022/ND-CP — fines plus suspension of operations until a permit is obtained. Every inspection from now on starts from the violation, not from the paperwork.
The only exit: stop the bleeding, then file
Step 1 — assess whether you can lawfully keep running while filing. Strictly speaking, no. In practice, an immediate voluntary shutdown followed by urgent filing demonstrates good faith and usually avoids the heaviest sanction tier. Continuing to run while “waiting for the permit” converts a remediable administrative lapse into evidence of deliberate violation.
Step 2 — file for re-issuance immediately under the procedures of Decree 08/2022/ND-CP. Prepare the full dossier: environmental monitoring reports, waste treatment system records, and an explanation of the lapse. Do not backdate or fabricate documents — a forged dossier discovered later turns an administrative case into a criminal one.
Step 3 — use voluntary disclosure. Article 9 of the Law on Handling of Administrative Violations (as amended in 2020) treats voluntary disclosure as a mitigating circumstance. A business that self-reports the lapse and urgently files is sanctioned far more lightly than one caught mid-violation.
Prevention: the permit diary no plant should lack
Permit expiry is a management failure, not a legal trap. Every plant needs a compliance calendar: permit expiry dates, monitoring report deadlines, periodic inspection dates — with alerts 6 months and 3 months before expiry, and a named person responsible. Renewal dossiers take months to prepare (monitoring data, system assessments); starting 6 months early is not cautious, it is normal. The cost of a calendar: zero. The cost of four months without a permit: fines, suspension, and a violation record that follows the company into every future licensing procedure.
Related articles
- Location Confirmation Letter from the Industrial Park Management Board
- Technology Explanation: When Required and What to Write?
- Investment Project Proposal: Writing Objectives, Scale and Schedule
- Land/Factory Lease Contracts: Mandatory Clauses for the IRC Dossier
- Parent Company's Investment Decision: Mandatory Contents
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.