Real Estate and Construction

What Should a Factory Lease Contract in an Industrial Park Contain?

Industrial warehouse interior

Leasing a factory inside an industrial park (IP) is nothing like renting an office or a house: the lessor may not own the land but merely sub-lease it, the lease term is “locked” to the IP’s remaining land tenure, and a host of shared-infrastructure charges simply do not exist in ordinary leases. This article lists the 14 mandatory contents of a factory lease contract under Clause 1, Article 46 of the Law on Real Estate Business 29/2023/QH15 (effective 1 August 2024, guided by Decree 96/2024/ND-CP), plus 5 IP-specific clauses that standard templates omit — written from the tenant’s (defensive) perspective, especially useful for FDI enterprises.

1. Why an IP factory lease differs from an ordinary lease

Three core differences: (1) the lessor is often an IP infrastructure business sub-leasing land/infrastructure — its legal standing determines your contract’s validity; (2) the lease term is tied to the IP’s remaining land-use term; (3) the factory depends on shared technical infrastructure (power, water, wastewater treatment, fire safety) the tenant cannot arrange alone. Miss any of these and the business may end up “stuck” with an unusable factory or a void contract.

2. Fourteen mandatory contents under Article 46 of the 2023 Law on Real Estate Business

#Statutory contentNegotiation notes (tenant’s view)
(a)Names and addresses of the partiesExact legal names, enterprise codes; the signatory must have authority (check the power of attorney)
(b)Real-estate informationPlot location, factory area, handover condition (as-built drawings, handover minutes with photos)
(c)RentUnit price/m²/year, VAT inclusive or not; price-adjustment mechanism per cycle (avoid vague “as agreed” — state a formula or cap)
(d)Payment method and termPayment cycle, grace period, late-payment interest; deposit amount and refund timing
(e)Bank guaranteeNot applicable to leases (only to off-plan housing sales) — if a lease demands a “guarantee,” it is voluntary; scrutinize trigger conditions
(f)Handover timing and accompanying dossierSpecific handover date, handover standards (flooring, power, fire safety); handover minutes as the rent-calculation basis
(g)WarrantyScope covering structure, roofing, technical systems; warranty period; who bears natural wear-and-tear vs misuse repairs
(h)Rights and obligations of the partiesTenant’s repair/renovation rights (prior consent needed?); lessor’s maintenance duties
(i)Liability for breachList each party’s specific breaches; avoid generic clauses
(j)Breach penaltiesPenalty levels and calculation; state whether penalties exclude damages
(k)Termination/cancellation and handlingUnilateral-termination events; notice periods; treatment of the tenant’s assets and machinery on termination
(l)Dispute resolutionNegotiation → mediation → arbitration/court; FDI tenants should consider arbitration clauses (VIAC/SIAC) and governing law
(m)Effective date of the contractPer Clause 6, Article 44: the moment the last party signs, unless otherwise agreed; if notarized, per the notarization date

Note on model contracts (Articles 44–45): the Government prescribes model contracts for real-estate business; real-estate businesses must publish their model contract before applying it. Notarization of leases is as agreed by the parties — not mandatory by law, but for high-value contracts notarization strengthens evidentiary value.

3. Five IP-specific clauses: a pre-signing checklist

Specific 1 — The lessor’s sub-leasing standing. Verify: does the lessor hold lawful land-use rights (one-off vs annual land rent under the Land Law 31/2024/QH15); has it settled financial obligations to the State; is it permitted to sub-lease. Request the land-use-right certificate and the IP Management Board’s approval (if any).

Specific 2 — Term tied to the IP’s land tenure. The factory lease cannot exceed the IP’s remaining land-use term. Negotiate a priority renewal clause synchronized with the infrastructure developer’s land extension; spell out the tenant’s rights if the IP’s land is not extended.

Specific 3 — Shared-infrastructure fees. Beyond factory rent, the business pays management fees, wastewater-treatment fees, common-infrastructure maintenance… Demand an itemized schedule of every charge, unit prices, adjustment mechanisms, cross-checked against the IP’s management regulations. This “hidden cost” item causes the most disputes.

Specific 4 — Fire safety and environment. Specify: which standard the existing fire-safety system meets, who bears upgrade costs if authorities require; whether the factory’s wastewater system can connect to the IP’s common system; who owns environmental-monitoring duties.

Specific 5 — Industries conforming to the IP’s plan. The lessor’s commitment that the tenant’s manufacturing lines conform to the IP’s plan and investment-attraction orientation; tenant protection if the IP changes its industry orientation (early termination rights, relocation-cost compensation).

4. Negotiation leverage points for tenants

Beyond checking boxes, tenants should negotiate five points where IP leases are most flexible. (1) Rent-free fit-out period: 1–3 months for installing machinery and production lines is customary — get it in writing, with the rent clock starting only after handover acceptance. (2) Rent-increase caps: replace “adjusted as agreed” with a formula — e.g., capped at CPI or a fixed annual percentage — to prevent mid-term rent shocks. (3) Early-termination rights: if the tenant’s investment license is revoked or the IP changes its industry orientation, the tenant should have a walk-away right with defined compensation, not a lock-in. (4) Assignment and subletting: the right to assign the lease or sublet surplus space (with lessor consent not unreasonably withheld) preserves flexibility if production scales down. (5) Renewal options: a pre-agreed renewal rent mechanism beats renegotiating from zero at expiry — link it to market rent with an independent valuation fallback.

Frequently asked questions

Can the tenant mortgage its lease rights? Lease rights for the remaining term can generally be used as loan collateral with the lessor’s cooperation, subject to bank requirements — clarify this in the lease to avoid a later refusal.

Who pays for factory expansion? Any expansion beyond the approved design needs a new or amended construction permit and the lessor’s/IP Board’s consent. Allocate these costs and the ownership of the expansion works in the lease upfront.

What if the IP developer goes bankrupt? The tenant’s registered lease survives against a successor, but in practice enforcement is messy. Mitigate by verifying the developer’s financial health at signing and registering the lease where possible.

Working with the IP Management Board: treat the Board as a partner, not just a licensing counter. Before signing the lease, request a pre-consultation on three items: confirmation that the tenant’s industry lines are consistent with the IP’s approved plan, the applicable fee schedule for shared infrastructure, and any upcoming planning adjustments that could affect the plot. Boards that are engaged early tend to process the later permit file faster — and a written pre-consultation record is invaluable if disputes arise about what was promised regarding the plot’s permitted use.

Conclusion

A compliant IP factory lease = the 14 statutory contents (Article 46, 2023 Law on Real Estate Business) completed fully and specifically + the 5 IP-specific clauses (sub-leasing standing, term tied to IP land, infrastructure fees, fire safety/environment, conforming industries) carefully checked. For the tenant, the three most important pre-signing tasks: verify the lessor’s legal standing, lock an itemized infrastructure-fee schedule, and pin down the term + renewal provisions.

This article provides reference information under the law as of 14 October 2026 (Law on Real Estate Business 29/2023/QH15, Decree 96/2024/ND-CP, Land Law 31/2024/QH15). Specific clauses should be reviewed by counsel according to the legal status of each IP and lessor.

This article has been reviewed by the QA Council — FLAW AI Legal Council.