Short answer: Two regulatory pressures are arriving together for Vietnamese data centers: fire safety specific to lithium-battery rooms and gas suppression systems, and energy efficiency measured by PUE. One point must be stated plainly: at the time of writing (20/10/2026) the general fire framework is already mandatory, but a binding PUE ceiling for data centers is still emerging — smart investors design ahead of the policy signals instead of retrofitting after the rule lands.
Fire safety: the general frame binds now; DC specifics live in design detail
The Law on Fire Prevention, Fighting and Rescue 55/2024/QH15 (effective 01/7/2025) is the current frame for fire design appraisal, acceptance and safety management of premises; data centers are among the works that must complete these procedures before operating. The data-center specificity lies in scenarios general codes do not fully describe: battery and lithium-storage rooms with thermal-runaway risk, server halls using clean-agent suppression that demand room-integrity control and occupant safety, and dense cable corridors. Appraisal practice handles these through design solutions and technical justifications in the dossier — the design team must proactively prove safety equivalence rather than wait for a dedicated data-center code. Compulsory fire and explosion insurance for listed premises now follows Decree 105/2025/ND-CP (replacing the expired Decree 23/2018/ND-CP), as amended by Decree 347/2026/ND-CP effective 15/9/2026.
PUE: no statutory cap yet — but already the market’s language
PUE — total facility energy divided by IT energy — is more efficient the closer it is to 1. Vietnam has enacted no maximum PUE for new data centers at the time of writing; yet the metric already appears in green digital-infrastructure policy direction, in international customers’ requirements and in long-term power-cost maths. A low-PUE design is decided on day one: hot/cold aisle architecture, liquid cooling for high-density GPU clusters, waste-heat reuse and renewable power through direct power purchase arrangements where eligible. Retrofitting a live data center to cut PUE costs many times more than designing correctly at the start — which is why energy-compliance cost belongs in the total investment as a rule-anticipating line, not as an afterthought.
Recommendations for investors
- Engage designers experienced in justifying fire solutions for battery rooms and gas-suppressed halls.
- Set an internal design PUE target and write it into cooling and power procurement.
- Reserve space and structural capacity for next-generation cooling technology.
- Budget fire and energy compliance as a separate line in total investment.
Frequently asked questions
How are data-center-specific fire rules being developed?
Data centers currently apply the general fire frame of Law 55/2024 and related technical regulations and standards; specifics such as lithium batteries, gas suppression and cable density are handled through design solutions and justifications in the appraisal dossier. Sector-specific requirements for digital infrastructure are expected to be progressively detailed, so design should anticipate rather than aim at today’s minimum.
Is there a maximum PUE requirement for new data centers?
At the time of writing (20/10/2026), no instrument sets a mandatory PUE ceiling for data centers in Vietnam. PUE is currently a design and commercial metric — driven by international customers and power costs — but investors should design competitively because energy-efficiency rules for digital infrastructure are forming and post-operation retrofits are expensive.
How can a green data center design anticipate the rules?
Three design-stage decisions: hot/cold aisle architecture and liquid cooling for high-density zones; power and cooling equipment selected on efficiency at real load, not nameplate load; and provision for renewable power and waste-heat reuse. Write the PUE target into procurement conditions so contractors answer for the number they promised.
How much of total investment does compliance cost?
There is no statutory ratio; fire and energy compliance cost depends on scale, Tier level and power density. The correct approach is a separate budget line in total investment from the outset — appraisal, dedicated equipment and periodic inspection included — rather than a surprise after the design is locked.
Related articles
- 2026 Policy Interest Rates: Forecasts and Borrowing Strategy
- Stock Market Upgrade (FTSE): Remaining Legal Conditions
- Financial Inclusion: Policies and Fintech Opportunities
- NPL Resolution (VAMC): New Mechanisms and Debt Trading Market
- Independent Audits of Credit Institutions: New Requirements
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.