One morning the plant receives a notice from the industrial park infrastructure developer terminating the land sub-lease and demanding site handover within a few months. On that site stand a built factory, a running production line and several hundred workers. The response in the first thirty days decides almost the entire legal position of the secondary investor for the following two years.
First question: does the termination stand legally at all
A land sub-lease inside an industrial park is a contract, and the developer unilateral termination right is locked by that contract together with the Civil Code 91/2015/QH13. Under Article 428 of the Code, a party may terminate unilaterally only where the contract grants that right, or where the other party has seriously breached its obligations to the point that the aggrieved party fails to achieve the purpose of contracting, and the terminating party must give advance notice within the period the contract sets or a reasonable period. A termination notice citing general reasons such as park restructuring or another internal use need, tied to no specific breach by the secondary investor and grounded in no termination clause of the contract, is a notice whose validity can be challenged.
The immediate task is to freeze your own compliance evidence: the payment history for rent and infrastructure fees, handover and acceptance minutes, construction investment records, and all correspondence with the developer over the last twelve months. At the same time, send a formal objection within the contract deadline for answering notices, stating that the notice is groundless, the contract remains in force, and that any cut of power or water, gate blocking or production obstruction will be recorded as damage evidence. That objection letter is the first brick of both the compensation file and any later lawsuit.
Money: compensation heads and quantifying them from day one
If the termination breaches the contract, the secondary investor may claim actual damages under the Civil Code, plus a breach penalty where the contract agreed one, and may demand continued performance as the preferred remedy where the plant cannot relocate at short notice. Damage heads must be quantified from the books as the dispute begins: the residual value of the factory and works on the land, dismantling and line relocation costs, production stoppage losses and penalties owed to customers for failed deliveries, replacement site costs during transition, and the rent differential at the new location for the remaining term of the old contract.
One head is routinely forgotten: labour cost of relocation, covering job-loss allowances and re-hiring and re-training expense at the new site under the Labour Code. Every head needs original vouchers and, for a large dispute, an independent quantification report, because courts and arbitral tribunals compensate proven loss only, not a sense of grievance at the termination notice.
The factory on the land and the choice of forum
The factory and works the secondary investor built on leased land are that investor property, separate from the infrastructure developer land use right. When the sub-lease ends, the fate of those assets follows the sub-lease itself: well-drafted leases carry a ready option for the developer to buy the works back at independent valuation, or for the investor to dismantle and return the site within a defined period. Where the lease is silent, treatment must be negotiated on the foundation of ownership of land-attached assets under the Land Law 31/2024/QH15, the weakest ground for an investor who failed to settle the point when the original lease was signed.
On forum, the dispute clause of the sub-lease decides first: arbitration if the contract chose it, court if not. Note that disputes directly concerning land use rights carry their own court jurisdiction at the property location, so even with an arbitration clause, claims of a land registration nature may still have to return to court. In parallel with litigation, working the channel of the industrial park or economic zone management board and the provincial investment authority is a practical front worth keeping open, because the infrastructure developer operates within an approved investment project and is supervised on its performance of that project.
Frequently Asked Questions
Is a unilateral termination lawful?
It is lawful only if it falls squarely within a ground agreed in the sub-lease or the statutory ground in Article 428 of the Civil Code 91/2015/QH13: a serious breach by the tenant defeating the developer purpose in contracting, with advance notice within the contract period or a reasonable period. A termination driven by the developer restructuring or internal needs, tied to no breach of the secondary investor, breaches the contract, can be challenged for validity, and triggers compensation liability.
Can compensation be claimed?
Claim the heads of actual, provable loss: residual value of the factory and works, dismantling and production line relocation costs, stoppage losses and penalties payable to customers for failed deliveries, replacement site cost and the rent differential for the remaining term, plus relocation labour costs. Add the contractual breach penalty where one was agreed under Article 418 of the Civil Code. Every head needs original vouchers and should be quantified by an independent firm from the start of the dispute.
How should the already-built factory be handled?
A factory built by the secondary investor is that investor property, separate from the developer land use right. At the end of the sub-lease it is treated as the lease provides: developer buy-back at independent valuation, or investor dismantling and site return within the agreed period. If the lease says nothing, treatment is negotiated on the basis of ownership of land-attached assets under the Land Law 31/2024/QH15, and the investor should obtain an independent valuation of all works before signing any handover minute.
Where should a lawsuit be filed?
Follow the dispute clause of the sub-lease: arbitration where the parties chose it, court where they did not. Claims directly concerning land use rights fall under the court at the property location under the Civil Procedure Code 92/2015/QH13. In parallel, the investor should engage the industrial park or economic zone management board and the provincial investment authority, because the infrastructure developer is supervised on performance of its approved project.
Related articles
- Leasing Land and Factories in Industrial Parks in Vietnam
- Acquiring Agricultural Land Use Rights in Vietnam: Conditions and Area Limits
- Foreigners' Land Use and Home Ownership in Vietnam: Scope and Limits
- Design Error Disputes in Vietnam: Liability of Designers and Builders
- Contractor Abandonment Mid-Project in Vietnam: Calling Guarantees, Hiring Replacements and Damages
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.