Leasing Land in Newly Established Industrial Parks Without Complete Infrastructure in Vietnam: Developer Completion Commitments

Drone photo of an active construction site in Quebec City, showcasing equipment and layout

Scenario: a new industrial park opens phase one: rents 25% below filled parks, but internal roads 60% built, the wastewater plant under construction, and official power promised “by year-end”. Signing a lease here is buying an infrastructure promise with real money. This article analyses how to price and lock the risk of leasing in an unfinished park — a decision that is not wrong if the contract turns promises into sanctioned milestones.

The nature of the risk: your rent is financing the infrastructure

In the new-park model under Decree 35/2022/ND-CP and Article 202 of the Land Law 31/2024/QH15, the developer leases land from the State and builds infrastructure from its own and raised capital — of which sub-lease money from early investors is a major source. That structure creates a dependency loop: infrastructure completes only if land sells, and land sells only if investors believe infrastructure will complete. The early tenant must see its position clearly: it is part-financing the very infrastructure it will use. Consequently, all protection revolves around two axes — money must not run ahead of verified physical progress, and schedule commitments must carry automatic sanctions rather than general damages duties enforceable only through court. Derivative risks (the park’s environmental license for full-capacity phases, detailed plans for each zone, the un-accepted wastewater plant) must also be asked outright in due diligence instead of assuming “open for sale means fully eligible”.

A standard infrastructure milestone set for new-park leases

Translate the factory’s operating needs into contract milestones across four systems. Power: the date of official supply at the plot’s connection point with committed capacity (kVA) in numbers, distinguished from temporary construction power. Water and wastewater: the date clean water reaches the factory’s design pressure/flow, and the date the park’s central wastewater plant is accepted and ready to receive the factory’s standard-compliant discharge — the latter is the milestone that slips most because it depends on environmental acceptance. Transport: the date the internal road from the park gate to the plot has its finished surface and container-truck load rating, excluding temporary construction roads. Legal base: the date the developer completes its land certificate for the project’s area and the zone’s detailed plan is approved. Each milestone carries three things: completion evidence (acceptance/connection records), automatic delay sanctions (proportional fee relief), and a final long-stop for termination with refunds. Such a milestone table takes two pages of the contract and saves years of disputes.

Negotiation strategy for the early mover

The early tenant holds real leverage: it is cash flow and market proof the developer uses to attract the next investors. That leverage should be traded for four things, in value order: a lower rent with a long-term adjustment cap (avoiding catch-up hikes the moment infrastructure completes); the schedule-protection clauses above; an option to expand into adjacent area at pre-fixed terms (cheap new-park land is a chance to reserve growth space); and a priority right to re-select a better plot in the park if the original is hit by planning adjustments. Conversely, what must never be traded for cheap rent is unsecured early payment: paying 70–100% of lump-sum rent for unbuilt infrastructure is an unsecured, zero-interest loan to the developer at full risk. If the developer needs money early, the correct structure is a bank advance-refund guarantee from its bank, or third-party escrow disbursed against acceptance milestones.

Frequently Asked Questions

What are the risks of signing a lease in a new industrial park with unfinished infrastructure?

Four risks attach directly to ‘unfinished’: (1) schedule — technical infrastructure (roads, power, water, wastewater treatment) slipping behind commitments leaves a built factory unable to operate; (2) temporary quality — interim connections (temporary power, temporary roads) cost extra and do not meet long-term operating standards; (3) immature legality — new parks often come with zoning adjustments in process, the developer’s certificate incomplete, and the park’s environmental license not yet issued for full operation; (4) the developer’s finances — new parks sell land to fund infrastructure, so slow sales mean slow infrastructure, and the risk concentrates exactly on the commitment the tenant relies on. In exchange, new-park rents are usually materially lower — the task is pricing the risk into the contract, not avoiding new parks altogether.

How should the developer’s infrastructure schedule commitments be contracted?

Verbal or brochure commitments are unenforceable. The sub-lease needs four components: (1) a table of specific infrastructure milestones tied to the project’s own needs (the date of official power at a stated capacity at the plot boundary, water date, the date the park’s wastewater plant accepts discharge, the date the internal road to the plot is complete) — never a generic ‘synchronised infrastructure completion’; (2) ‘completion’ defined by technical standards (capacity, pressure, quality) with acceptance/connection records as evidence; (3) automatic sanctions: delay triggers rent and fee relief proportional to the delay, with the delay period added to the lease term; (4) a long-stop date: past a fixed date without essential infrastructure, the tenant may terminate and recover all money and deposits. Without components (3) and (4), a schedule commitment is only a declaration of goodwill.

How should rent payments be structured in a new park to keep leverage?

The golden rule: money follows infrastructure milestones, never precedes them. A practical three-stage structure: a small reservation deposit (under Article 328 of the Civil Code 91/2015/QH13, with a refund condition); a second payment at formal signing tied to legal milestones (the developer’s land lease decision, the plot’s detailed-plan approval); and the main instalments released only when the corresponding infrastructure milestone is accepted on site (power at the plot boundary, water, road). Absolutely avoid paying most of the contract value (especially under the lump-sum option) before core infrastructure exists — once paid in full, the tenant loses all schedule leverage and that money becomes unsecured financing for the developer’s project. If the developer asks for early payment ‘to fund infrastructure’, that is the signal to negotiate a bank advance-refund guarantee or a risk-commensurate discount.

How can the developer’s capacity to complete infrastructure be verified?

Four verification layers: project documents (the infrastructure project’s Investment Registration Certificate, the land lease decision, investment progress against commitments to the registration authority — the park Management Board knows exactly which projects lag their registration); the field (what percentage of infrastructure is actually built, and whether construction is moving or standing); earlier investors (how factories that entered earlier are operating, whether their connections were delayed — the most truthful information source); and finance (whether the developer has mortgaged the whole project to a bank, and whether its land-rent obligations to the State are fulfilled). Every layer must produce a written output or current-status photos filed in the due-diligence record, for later comparison against contract commitments.