A building deteriorates during the warranty period — whom does the project owner claim against: the main contractor or the subcontractor who actually performed the work? The answer lies in how the law allocates liability between these two parties. Misunderstanding the liability chain can lead the owner to claim against the wrong party and prolong disputes.

Main contractor vs subcontractor: defined by contracting counterparty

The Construction Law 2025 (No. 135/2025/QH15, effective from 1 July 2026) defines these two parties based on whom they contract with:

  • Main contractor: a contractor entering into a construction contract directly with the project owner (Clause 26, Article 3);
  • Subcontractor: a contractor entering into a construction contract with the main contractor (Clause 27, Article 3).

In other words, the subcontractor has no direct contractual relationship with the project owner — the pivotal point of the entire liability chain.

Quality liability: who answers to whom?

Under Point l, Clause 2, Article 61 of the Construction Law 2025:

  • The main contractor (construction contractor) is liable for construction quality in accordance with the approved design, including work performed by subcontractors (if any), before the project owner and before the law;
  • The subcontractor is liable for quality only for the work it performs, before the main contractor and before the law.

At the same time, the construction contractor must warrant the works within the scope of work performed under the construction contract (Point i, Clause 2, Article 61).

The warranty liability chain

From these provisions, the liability chain is established as follows:

Project owner → claims against the main contractor (for the whole works, including subcontracted portions) → main contractor → recovers from the subcontractor (within the subcontractor scope of work).

The project owner has no direct contractual relationship with the subcontractor and therefore cannot claim directly against it, unless otherwise agreed or otherwise provided by applicable law.

Warranty periods and warranty money

Under Article 28 of Decree No. 06/2021/ND-CP (still in force):

  • At least 24 months for special-grade and grade-I works using public investment capital or non-public-investment state capital;
  • At least 12 months for other grades of works using public investment capital or non-public-investment state capital;
  • For works using other capital, the warranty period is as agreed by the parties in the contract (the above levels may be used as reference).
  • Warranty money: 3% or 5% of the contract value for works using public investment capital or non-public-investment state capital.
  • The warranty period is counted from the project owner acceptance of the works.

Important note: the 12/24-month levels are mandatory only for works using public investment capital / non-public-investment state capital. It is incorrect to say that “all works must be warranted for at least 12 or 24 months” — for private capital, the period is as agreed by the parties.

Comparison: main contractor vs subcontractor

CriterionMain contractorSubcontractor
DefinitionContracts directly with the project owner (Art. 3.26, Construction Law 2025)Contracts with the main contractor (Art. 3.27, Construction Law 2025)
Quality liabilityFor the whole works, including subcontracted portions — before the owner and the lawFor its own scope of work — before the main contractor and the law
WarrantyWithin the scope of work under the construction contract (Art. 61.2(i))Within its own scope of work
Relationship with ownerDirect (contractual)No direct relationship

Legal basis

  • Article 3.26, 3.27; Article 61.2(i), 61.2(l) of the Construction Law 2025 (No. 135/2025/QH15, effective from 1 July 2026).
  • Article 28 of Decree No. 06/2021/ND-CP (warranty periods and warranty money; still in force, as amended by Decrees 35/2023, 175/2024, 140/2025, 144/2025, 14/2026).

Validity note: the Construction Law 2014 has expired; its old provisions no longer apply.

Frequently asked questions

Can the project owner claim warranty directly against the subcontractor?
As a rule, no — the subcontractor has no direct contractual relationship with the owner. The owner claims against the main contractor, which in turn recovers from the subcontractor.

Must all works be warranted for at least 12 months?
No. The 12/24-month levels are mandatory only for works using public investment capital / non-public-investment state capital; private-capital works follow party agreement.

When does the warranty period start?
From the project owner acceptance of the works.

Facing a construction warranty dispute or need a construction contract review? Contact FLAT Law Firm via our contact page for support.

This information is for reference only and does not constitute legal advice.

See more articles on Real Estate and Construction.

Related articles

Reviewed by the Legal Practice Group – FLAT LAW FIRM

This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.