Scenario: a cold-storage seafood plant loses grid power for 14 hours; 40 tons of raw shrimp in the freezers spoil. The power company says: “force majeure — a transmission line fault”, case closed. The plant’s loss: billions of dong. Is “force majeure” really the end of the story — or the beginning of a claim?
Two kinds of blackouts, two opposite legal outcomes
Vietnamese power law distinguishes sharply. The 2024 Electricity Law (61/2024/QH15, effective 1 February 2025), Article 49: suspension or reduction of supply must follow the law and the signed power purchase contract — the parties must agree in the contract on the cases and the notification method.
Case 1 — scheduled or notified interruption. The seller must notify in advance (the classic rule: at least 5 days for non-emergency interruptions, announced over three consecutive days). If the plant received proper notice and still left 40 tons of shrimp in the freezers without backup, the loss is substantially the plant’s own fault.
Case 2 — sudden interruption without proper basis. Where the power company suspends or reduces supply contrary to the rules on suspension/reduction — no emergency, no force majeure, no contractual ground — it faces administrative sanctions and, crucially, must compensate the buyer for resulting damage. The old law’s Article 27(3) stated this plainly, and the principle carries into the 2024 framework: unlawful interruption causing loss triggers compensation liability.
“Force majeure” is not a magic word — test it
A transmission fault is not automatically force majeure. Genuine force majeure means an event that is unforeseeable, unavoidable and insurmountable despite all reasonable measures — a typhoon toppling towers, for example. A fault caused by deferred maintenance, overloaded lines or known equipment defects is the seller’s negligence wearing a force-majeure costume. The plant has the right to demand: the incident report, maintenance records of the faulty line, and proof that all reasonable preventive measures were taken. If the power company cannot produce them, “force majeure” collapses.
Also check the notification duty: even in emergencies, the seller must notify the buyer of the cause and the expected restoration time within 24 hours. A 14-hour blackout with zero communication is itself a breach.
Building the claim: evidence the plant must gather now
Successful power-outage claims are won on documentation: (1) the power purchase contract — interruption clauses, notice requirements, liability terms; (2) the outage log — exact start/end times, ideally from the plant’s own monitoring plus the power company’s confirmation; (3) the damage inventory — quantity and value of spoiled materials with purchase invoices, plus disposal records and photos; (4) mitigation evidence — backup generator logs, attempts to save the goods (this defeats the “you didn’t mitigate” defense); (5) the power company’s incident explanation in writing.
And the strategic lesson: for cold-chain and continuous-process plants, a backup generator is not an expense — it is litigation armor. Courts and arbitrators consistently reduce awards where the buyer made no effort to mitigate a foreseeable risk.
Related articles
- Opening a Foreign-Invested Vocational College: How Conditions Differ from Training Centers
- Manufacturing Cosmetics in Vietnam: Factory Conditions and CGMP Certification
- Importing Refurbished Medical Equipment: Conditions and Permitted Lists
- Bioequivalence (BE) Studies for Generic Drugs: Research Facility Requirements
- Electrical Safety for DC Fast Charging: Mandatory Technical Standards
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.