Resolution 170/2024/QH15 is the instrument the real estate investment community names most when discussing unblocking stalled projects — and also the one most over-read in scope. The first fact to hold: this special mechanism in its original scope applies only to projects and land cases in three localities — Ho Chi Minh City, Da Nang and Khanh Hoa — attached to specific inspection conclusions, audits and judgments listed in the resolution’s annex. A stalled project in another province, or in these very three localities but outside the listed case group, does not automatically enjoy the mechanism.
The mechanism’s content and the unblocking conditions in Article 2
Resolution 170/2024/QH15 was passed by the National Assembly on 30 November 2024 to handle projects and land entangled in inspection conclusions, audits and judgments — the group of projects frozen for years by violations in land allocation, land price determination and certification in earlier periods. Article 2 of the resolution sets the core condition for unblocking: the handling mechanism applies only where the cause of the entanglement is the fault of state agencies or a mixed fault between state agencies and the investor, and unblocking is carried out only after the responsibility of violating organisations and individuals has been strictly handled and the economic consequences remedied as prescribed. For cases in criminal proceedings, the mechanism applies only after a legally effective judgment. The resolution also handles a separate group of 1,313 cases of land use term violations in certification. These three conditions reveal the mechanism’s nature: it is the State’s error-correction mechanism for the State’s own faults, conditional and verified — not a general amnesty for every delayed project.
Implementation status and the nationwide expansion story
Within the original scope, the covered localities have reviewed and processed most of the projects on their lists, out of more than two thousand stalled projects inventoried nationwide. The very gap between real nationwide demand and the three-locality scope led the Government to submit to the National Assembly the expansion of the Resolution 170/2024/QH15 mechanism to the remaining localities. At the time of writing, the expansion remains under consideration by the competent level and has not become a generally applicable instrument — an investor with a project outside the original scope must therefore distinguish the two legal states clearly: a project within the resolution’s annex is processed now under the current mechanism; a project outside scope can only prepare its file and track the expansion decision, with no basis to demand that a locality apply the mechanism by analogy today. Every commercial commitment built on the assumption that “the resolution will be expanded and our project will certainly be in scope” is a commitment on an event that has not happened.
What should an enterprise with a stalled project do in each case?
Where the project sits in the three localities and within the annexed case group: the work is to match the exact case code, complete the obligations on the investor’s side — remedying economic consequences, fulfilling outstanding financial obligations — and work directly with the local task force and assigned authority so the project enters the processing list by batch. Where the project is stalled outside scope: the correct strategy is building the file proving the entanglement’s nature as state agency fault or mixed fault — wrong-period land pricing, ultra vires land allocation, planning changes after project deployment — because this is exactly Article 2’s screening criterion and will be the criterion of any expansion mechanism; in parallel, review the ordinary handling channels that remain open, such as planning adjustment, schedule extension and financial obligation re-determination under current land law, instead of freezing in wait for the special mechanism alone. And in both cases, appraising the acquisition of a stalled project must price it on its real legal status at the transaction date — never on unblocking expectations.
Frequently Asked Questions
Which projects are covered by the pilot mechanism for resolving land entanglements under the National Assembly’s resolution?
In its original scope, Resolution 170/2024/QH15 dated 30 November 2024 applies to projects and land entangled in inspection conclusions, audits and judgments in three localities: Ho Chi Minh City, Da Nang and Khanh Hoa, per the case list in the resolution’s annex, plus the group of 1,313 land use term violations in certification. A project in another locality, or in these three localities but outside the listed cases, is not within the direct application scope and must await a formal expansion decision.
What are the conditions and sequence for a stalled project to be placed on the resolution list?
The core conditions in Article 2 of Resolution 170/2024/QH15: the entanglement’s cause must be the fault of state agencies or mixed fault between state agencies and the investor; the responsibility of the violating organisations and individuals must have been strictly handled as prescribed; the economic consequences must be remedied; and for cases in criminal proceedings, there must be a legally effective judgment. A project delayed purely by the investor’s own fault — capital shortage, slow construction — is not within this mechanism’s unblocking scope.
Does the resolution mechanism apply to an FDI project that has been stalled for many years?
Only within the mechanism’s narrow scope, and ‘stalled for many years’ is not itself a qualifying criterion. A stalled FDI project falls within the handling scope only if it meets two layers of conditions at once: it belongs to the case list in the annex of Resolution 170/2024/QH15 in one of the three localities — Ho Chi Minh City, Da Nang, Khanh Hoa; and the cause of the entanglement is the fault of state agencies or mixed fault between state agencies and the investor under Article 2, with the responsibility of violating organisations and individuals handled and economic consequences remedied. A project stalled for the investor’s own reasons — capital shortage, slow construction, strategy change — is outside this mechanism’s resolution scope however many years it has stood still. For out-of-scope projects, the Government has submitted to the National Assembly consideration of extending the mechanism to the remaining localities, but no generally effective extension decision exists yet; the right strategy is to prepare the file proving state-agency or mixed fault, while using the ordinary handling channels of current land and investment law.
After being unblocked, within what time must the project complete its financial obligations and schedule?
Resolution 170/2024/QH15 sets no single uniform completion deadline for all unblocked projects. Once a case is placed in the handling scope, outstanding financial obligations must be completed and economic consequences remedied as conditions of the resolution under Article 2; the specific timetable for each project — completing financial obligations, restoring and securing construction progress — is fixed in the decision and handling plan of the competent authority and the local task force case by case. The practical consequence is that the enterprise cannot infer a ‘common deadline’ from the resolution text itself: what must be done is to match the project’s exact case code, complete the obligations on the investor’s side, and work directly with the assigned task force to lock the commitment schedule in writing — a project late in completing its own obligations is a project losing its place in the batch-by-batch handling list.
Pin down the unblocking scope for your project with FLAT Law Firm
FLAT Law Firm matches the stalled project against the annex of Resolution 170/2024/QH15 and Article 2’s fault criteria, builds the mixed-fault evidence file for out-of-scope projects awaiting expansion, and structures milestone pricing clauses in stalled project acquisitions.
Related articles
- Renovating Your Apartment: What Foreign Owners Must Get Approved
- Pets in Apartments: Rules Foreign Owners Must Know
- Parking Space Disputes: Cars, Motorbikes and Your Rights
- Buying an Officetel: Foreigners and the 50-Year Certificate
- Incentives for Social Housing Developers: Land-Use Fee Exemption, Taxes and the 10% Norm Profit — Conditions and Post-Project Inspection
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.