Almost every land user whose land is recovered feels the compensation is low; winning the case is a matter of price evidence. A site-clearance compensation suit is in substance a duel between two valuation systems: the State’s specific land price and the market price the land user can prove.
Legal basis
- Land Law 31/2024/QH15
- Law on Complaints 02/2011/QH13
- Law on Administrative Procedures 93/2015/QH13
How compensation prices are set under the Land Law 2024
On recovery, land compensation uses the specific land price decided by the competent state authority when approving the compensation plan, built on the land price table and the valuation methods of the Land Law 31/2024/QH15 (comparison, income, residual, extraction). Assets attached to land (factories, structures, crops) are compensated under their own frames. Attacking the price starts with obtaining the valuation file behind the plan: which method was used, which comparable transactions were chosen — material the business is entitled to request.
The route: complain against the plan first, then sue — with independent price evidence
The land user complains against the plan/approval decision under the Law on Complaints 02/2011/QH13, attaching an independent valuation certificate for the land and attached assets, plus real transaction data for similar plots in the area. Unlike comments at the plan-consultation meeting (often minuted and ignored), a complaint obliges the authority to answer point by point in writing. If unsatisfied, sue administratively to annul the approval and compel revaluation.
Amounts beyond “land price” that are often missed
Many files argue only the unit land price and overlook amounts of equal weight: support for stabilising livelihood and production, training/job-change support (for agricultural land), compensation for impaired use of the remaining land, dismantling and machinery-relocation costs, and business losses from production stoppage during relocation. For an FDI manufacturer, this “actual loss” group can exceed the unit-price gap — and it must be itemised and evidenced in the complaint file from the start.
Related reading on flaw.vn: article FDI-LC-2327 covers the general framework of this topic — this article deals only with the specific angle in its title.
Frequently asked questions
If compensation is low, where do I sue?
Complain against the decision approving the compensation plan within 90 days under the Law on Complaints 02/2011/QH13, or sue administratively under the Law on Administrative Procedures 93/2015/QH13 after the complaint tier as prescribed. In practice: the complaint lets you add an independent valuation certificate so the authority can correct its own plan; the lawsuit moves review of the plan’s legality to an independent court.
Request revaluation?
Evidence comprises: an independent valuation firm’s certificate for the land and attached assets, real transfer-transaction data for similar plots in the same area and period, and the valuation file the State used for the plan (request it to compare method and comparables). Without an independent certificate, a demand for higher compensation is little more than an opinion.
Grounds to increase compensation?
Yes — it is one of the first steps to take: an independent valuation is both evidence for the complaint/suit and the yardstick for deciding whether the fight is worth it. Choose a licensed valuation organisation and require methods recognised by the Land Law 31/2024/QH15 — the engagement of valuers is treated in depth in the separate article on compensation valuation.
Limitation period?
Beyond land price, review: production/livelihood stabilisation support, dismantling and equipment-relocation costs, losses from production stoppage during relocation, compensation for assets attached to land, and impairment of the remaining land’s usability. These must be itemised with evidence in the complaint file from the outset, as late additions are usually refused.
Related articles
- Construction Permits for Projects in Vietnam
- Acquiring Agricultural Land Use Rights in Vietnam: Conditions and Area Limits
- Foreigners' Land Use and Home Ownership in Vietnam: Scope and Limits
- Design Error Disputes in Vietnam: Liability of Designers and Builders
- Contractor Abandonment Mid-Project in Vietnam: Calling Guarantees, Hiring Replacements and Damages
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.