Technology Transfer in BOT and BTO Contracts in Vietnam: Duties and Timing

Bridge Support Beams by the Road

Technology Transfer in BOT and BTO Contracts in Vietnam: Duties and Timing. FLAT regularly handles this issue when foreign investors deal with technology transfer duties in BOT and BTO contracts in Vietnam: one wrong step can trigger administrative fines, loss of asset rights or prolonged disputes. This article follows a lawyer’s review sequence: the legal basis in force as of October 2026, how it applies to a concrete file, the procedure to follow and the risks to settle before signing anything.

Core legal basis — technology transfer duties in BOT and BTO contracts

In BOT and BTO contracts the end-of-project transfer duty has two layers often merged: transfer of the project works to the State under the PPP Law 64/2020/QH14 and the project contract, and transfer of the operating technology embedded in those works under the Law on Technology Transfer. The second layer decides whether the State can actually run the project after handover: technical documents, operating procedures, personnel training and use rights in the intellectual property attached to the technology.

Applying the rules to your situation

BOT technology transfer disputes rarely concern whether transfer happens; they concern the standard of the technology at handover: are documents updated to the operating version, is trained staff certified to run independently, and do control-software licences continue or expire with the project contract? These standards must be quantified in the project contract at signing, because by handover year both sides have incentives to read ambiguity in their own favour.

Procedure and documents to prepare

  1. Step 1: separate in the project contract the works-transfer schedule from the technology-transfer schedule: documents, operating data, training and IP needing continued licences.
  2. Step 2: attach measurable handover standards: technical condition, latest-version document sets, training hours and output standards, and post-handover operating support time.
  3. Step 3: register the technology transfer under Decree 101/2026/ND-CP where the transfer falls in a registrable category, and settle tax and licence fees for IP licensed on after handover.
  4. Step 4: accept the transfer in stages with a separate technology acceptance minute (not merged into the works handover minute), listing shortfalls and cure deadlines.

Risks to anticipate

The first risk is a project contract that transfers works but is silent on technology: the State receives physical assets it cannot independently operate. The second is control technology owned by subcontractors or foreign equipment suppliers, outside the project company’s power to transfer. The third is no valuation or sanction mechanism for transfer shortfalls, leaving almost no leverage to demand completion after the project contract ends.

Answers to client questions

Is technology transfer mandatory in a BOT contract?

Transfer of the works at contract expiry is the default structure of BOT and BTO under the PPP Law 64/2020/QH14; transfer of the operating technology is content the parties must specify in the project contract, and in practice it is the condition for the State to receive and self-operate the works. In addition, technology transfers in statutory categories must be registered under the Technology Transfer Law framework and Decree 101/2026/ND-CP.

When does technology transfer occur in a BOT project?

At the end of the project contract and works handover, unless the contract phases training and operating know-how transfer earlier. Good practice starts training and document handover at least one full operating cycle before the formal handover date, so the receiving side can run trial operations under the investor’s supervision.

What must the transfer include (documents, training)?

Three groups: documents and data (updated design files, operating and maintenance procedures, performance data); people (training and transfer of operating capability to an independent standard); and rights (continued licences for software and third-party technology needed to operate). Missing any group, the transfer completes only on paper.

What sanctions apply if transfer is incomplete?

Under the project contract: breach penalties, calls on the performance security, and damages for the State’s cost of substitute operation. Beyond contract, failure to perform a registrable technology transfer duty can draw administrative handling in the science and technology field. Specific sanction levels must be quantified in the contract, as the law sets no single level for all projects.

Action conclusion

When negotiating a BOT or BTO contract, draft the technology transfer annex like a standalone contract: schedule, standards, training, IP rights and sanctions. Every third-party technology needed for post-handover operation needs a continued-licence commitment secured at equipment procurement stage.