Six months after closing, a former customer sues the target for a product defect that occurred before the deal. The buyer wants the seller to pay; the seller wants to run the defence; and either side can wreck the case if the SPA did not pre-write the third-party claim indemnity procedure.
Notice: deadlines and the cost of late notice
A standard indemnity clause requires written notice within a short window (often 10–15 business days) of receiving the writ or claim, with full copies attached. The point to negotiate is the consequence of delay: fair drafting reduces the seller’s liability only by the loss the delay actually caused (for example, losing a first-instance appeal window), instead of forfeiting the whole indemnity — ‘late notice kills the claim’ language is routinely abused to reject even obvious claims.
Control of the defence: who drives the case
The seller paying the bill usually demands the right to appoint counsel and direct the defence; the buyer — named defendant and bearer of reputational risk — needs participation rights, information rights and, critically, a veto over settlements imposing non-monetary burdens on the company (public apologies, product recalls, process-change undertakings). Under the Civil Procedure Code 92/2015/QH13 only the party or its lawful representative may appear in proceedings, so a ‘seller-run defence’ must be implemented through authorisation and a tripartite legal-services arrangement — it does not flow automatically from the SPA.
Costs and outcomes: how they are allocated
Draft expressly: court fees, reasonable counsel fees and amounts awarded or settled fall inside the indemnity; administrative fines and losses caused by the buyer’s post-closing conduct fall outside. If the case is won, unused advances must be returned. Draw costs from the escrow while it lasts, and make the indemnity claim period outlive the third party’s own limitation period for the underlying event — otherwise the clause is an empty promise.
Frequently Asked Questions
Can an offshore seller defend directly before a Vietnamese court?
Not as a party — the defendant is the target or the buyer. The seller acts through an authorised defence arrangement and bears cost under the SPA; strategy control is a matter for the indemnity clause, but signatures on procedural documents must be the party’s or its lawful representative’s in Vietnam.
What if the buyer settles without asking the seller?
Where the SPA contains a settlement-consent clause, settling alone forfeits indemnity for the settled amount, unless the buyer proves the seller unreasonably refused to engage. Without such a clause, a reasonable settlement remains indemnifiable but the buyer must prove its reasonableness.
What if the claim arrives after the warranty period ends?
Distinguish the underlying event date from the claim date: most SPAs run the period to the date the buyer receives the claim, while tax and title warranties survive longer or follow statutory limitation. A late claim leaves only an ordinary contract action, with the three-year limitation under Article 429 of the Civil Code 91/2015/QH13, if breach already existed at closing can be proved.
Related articles
- Transition Service Agreements (TSAs) in Vietnam: Contents, Duration and Fees
- Separating IT Systems and Data in Carve-Outs in Vietnam: Plans and Risks
- Separating Trademarks and IP When Selling a Business Line in Vietnam
- Allocating Staff in Carve-Outs in Vietnam: Who Goes, Who Stays and Rights
- Separating Customer and Supplier Contracts in Carve-Outs in Vietnam: Novation
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.