A consortium that wins and then loses a member mid-performance is a headache for all three sides: the remaining member fears carrying the whole package, the project owner fears a broken project, and the departing member imagines a withdrawal letter ends its liability. Vietnamese bidding law does not treat a consortium as a loose grouping: under Clause 26, Article 4 of Bidding Law No. 22/2023/QH15, a consortium bids, signs and performs on the basis of a consortium agreement that must clearly state the lead member’s responsibilities and the joint and several responsibilities of each member for the entire package scope.
Can a departing member free itself of liability?
The short answer is no — at least not vis-a-vis the project owner. The consortium agreement is the basis on which the expert team evaluated the consortium’s combined capacity during selection, and the contract is then signed with the consortium as one contractor. A unilateral withdrawal notice changes neither fact: the capacity assessed was pooled capacity, and the performance commitment to the owner is the consortium’s commitment. If the departing member’s scope is not performed and no replacement plan is accepted by the owner, the whole consortium faces the consequences of contract breach: penalties, calling of the performance security under Article 68 of the 2023 Bidding Law, and damages. Where a withdrawal leaves the package unperformable and is viewed as distorting or abandoning bid commitments, exposure can even extend to debarment sanctions under Article 125 of Decree 24/2024/ND-CP in the cases the law prescribes.
Internally, a well-drafted consortium agreement usually anticipates this scenario: withdrawal and its consequences, handover duties for documents, personnel and equipment, internal indemnities for the remaining members, and a right to subcontract the abandoned scope. Where the agreement is silent, internal relations fall back to the 2015 Civil Code: the departing member must compensate the actual loss its withdrawal causes the others, and obligations already incurred towards third parties during its membership do not simply evaporate.
The remaining member: three tasks for the first week
Task one is to lock down evidence and dates: minute the withdrawal declaration and the state of the departing member’s scope (work done, documents held, whose staff the key personnel are), and formally demand handover performance. Task two is to report proactively to the project owner with a continuation plan: which scope the remaining member absorbs, which goes to a subcontractor, and how the overall schedule moves. That proactive posture decides whether the owner sees an “incident with a plan” or a “consortium in breach”; the owner holds situation-handling authority in bidding under Article 131 of Decree 24/2024/ND-CP, exercised on competition, fairness and feasibility grounds. Task three is to re-check the performance security and cash flows: whose name the security stands in, whose credit line is locked, and which owner payments for the departing member’s scope should be frozen in internal reconciliation until responsibilities are allocated.
What the project owner may — and may not — do
The owner is not obliged to accept an effectively new consortium in place of the one selected: changing members after bid closing, where it alters the capacity that was evaluated, is in principle impermissible because it would break fairness towards other bidders. But the owner may accept a cure plan inside the signed contract — allowing the remaining member to subcontract the abandoned scope, adjusting the schedule, or, where the consortium truly cannot perform, terminating under the contract and processing the consequences as prescribed. Owners and remaining members usually meet at one point: nobody gains from a cancelled package, so a credible continuation plan is preferred over termination whenever replacement capacity is proven.
Suing the departing member: what, and where
Internal claims come in three groups: replacement costs (subcontract price differences, re-mobilisation); the share of penalties and owner-side damages caused by the withdrawal; and repayment of advances for work never performed. The forum follows the consortium agreement’s dispute clause — commercial arbitration is a common choice for confidentiality — or the competent court. In parallel, remaining members should consider interim asset-freezing measures if the departing member shows signs of dissipating assets, because a winning judgment is only worth what remains enforceable.
Frequently Asked Questions
Who bears liability when a bidding consortium falls apart mid-way?
Towards the project owner, liability rests on the consortium as one contractor under Clause 26, Article 4 of the 2023 Bidding Law and the consortium agreement: a departing member cannot unilaterally shed liability for committed scope. Between members, liability follows the consortium agreement; where it is silent, the 2015 Civil Code rules on actual-loss compensation apply.
Must the remaining member carry the whole package alone?
The remaining member must keep the package performable, but not necessarily with its own resources: it may absorb part of the scope and subcontract the abandoned part, provided it reports to and obtains the project owner’s acceptance under the situation-handling mechanism in Article 131 of Decree 24/2024/ND-CP. Extra costs are recoverable from the departing member internally.
Can the project owner terminate when a consortium breaks up?
Yes, if the consortium can no longer perform and offers no accepted, feasible cure plan; the owner then terminates under the contract, processes the performance security under Article 68 of the 2023 Bidding Law, and claims damages. But the owner is not forced to terminate where a continuation plan proves replacement capacity.
Where do you sue a member that walks out of a consortium?
Where the consortium agreement’s dispute clause points: commercial arbitration if agreed, or the competent People’s Court. Claims cover replacement costs, penalties and owner-side damages caused by the withdrawal, and advances to be repaid for unperformed work.
Related articles
- First-Year Office/Headquarters Rent for an FDI Company
- Total Cost of Setting Up a Manufacturing FDI Company: Sample Budget
- Total Cost of Setting Up a Trading/Service FDI Company: Sample Budget
- Hidden Formation Costs: What Investors Forget
- Investor Passports: Legalization, Translation and Validity
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.