Fire Safety Acceptance Before Handover: Step-by-Step Procedures

Firefighter wearing helmet with flashlight

A fundamental change from 1 July 2026 that many FDI files have not caught up with

For years, the final milestone for a project subject to fire design approval was the police fire authority’s written acceptance of fire acceptance results after inspecting acceptance work under Article 10 of Decree 105/2025/ND-CP. That milestone has moved: Resolution 66.18/2026/NQ-CP of 18 May 2026 provides that from 1 July 2026 the fire acceptance inspection procedure in Article 10 of Decree 105/2025/ND-CP is no longer performed, including for projects already holding a design approval certificate but not yet an acceptance result approval under clause 3 of Article 46 of that decree. Instead, the investor self-organises fire acceptance under Article 8 of Decree 105/2025/ND-CP (with acceptance responsibilities just amended by Decree 347/2026/ND-CP, in force 15 September 2026) and answers to the law for the acceptance outcome.

The practical consequence is large: no police team arrives to inspect and sign off before opening day, but the procedural shield investors used to rely on is also gone. The burden of proving the works were built exactly to the appraised fire design shifts entirely to the investor, the supervision consultant and the contractor; the police move to periodic and surprise inspections after the project operates under Article 13 of Decree 105/2025/ND-CP, and violations found at that stage are handled as operating violations, not pre-acceptance file defects.

The step-by-step procedure under the current framework

Step one: complete construction of all fire items exactly to the appraised and approved design — alarm, suppression, fire separation, escape, fire water supply, lightning protection and fire-service electrical systems; every deviation from design must be resolved through design adjustment before acceptance, leaving no unregularised difference. Step two: test and technically verify systems and equipment as required — interlock testing of alarm, suppression, lifts and stair pressurisation, checking fire flow and pressure, and readiness of pumps and backup power. Step three: the investor organises internal acceptance with all parties present — contractor, supervision consultant, design firm — and compiles the acceptance report with completion acceptance minutes and as-built drawings of the fire systems and fire-service electrical systems; this is the dossier formerly filed with the PC15 inspection request, now the investor’s own acceptance file to keep and produce on inspection.

Step four: before putting the works into operation, the investor declares on the fire, rescue and fire-alarm transmission database system as amended by Decree 347/2026/ND-CP. Step five: complete parallel operating conditions — the facility fire plan, a trained in-house fire team, escape rules and signage, and periodic system maintenance. Only when this chain is complete is the project legally safe to put into use — the right order is fire acceptance completed before or together with construction completion acceptance, but always before actual operation day.

If self-acceptance fails, and the trial operation question

Failing acceptance — here, failing in the assessment of the investor and participating parties themselves — means the works may not be put into use; the investor must have the contractor rectify, retest and re-accept the failed parts. With no police sign-off remaining, deliberately operating a project whose fire systems do not pass will surface at periodic or surprise inspection or when an incident occurs, drawing administrative fire penalties and civil or criminal liability if a fire causes damage. Trial-running a production line before completing fire acceptance is a classic FDI trap: trial operation still counts as putting the works into use for the areas and systems involved; the safe pattern is to confine trials to the scope already accepted, with a written temporary fire plan and on-site fire watch personnel.

For FDI contractors, lock three contract clauses: the contractor is responsible for passing interlock testing before acceptance; the fire as-built dossier is a condition of the final payment instalment; and post-acceptance rectification liability, where a police inspection finds deviations from the appraised design, falls on the party that caused the deviation. With ex-post inspection replacing ex-ante approval, the contract is the only place this risk can be fairly reallocated.

Frequently asked questions

Is fire acceptance done before or after construction completion?

Fire acceptance is organised once fire items and systems are built and tested — at the end of construction, before or together with construction completion acceptance, and always before the works are put into use. Since 1 July 2026 it is an acceptance the investor self-organises under Article 8 of Decree 105/2025/ND-CP, with no police acceptance inspection step as before.

Who performs acceptance — must the fire police be invited?

The investor self-organises acceptance with the contractor, supervision consultant and design firm, and is legally responsible for the result. Under Resolution 66.18/2026/NQ-CP, from 1 July 2026 the police fire acceptance inspection under Article 10 of Decree 105/2025/ND-CP no longer exists; before operating, the investor declares on the fire database and alarm transmission system.

Is there a fine if acceptance fails?

A failing result in internal acceptance is not itself fined; the duty is to rectify and re-accept, and the works may not be used yet. Penalties arise when a project is put into operation with fire systems not passing or deviating from the appraised design — handled administratively in the fire field at periodic or surprise inspections, with far heavier liability if a fire occurs.

Can trial operation run before acceptance?

It should not, and it is legally unsafe: trialling on areas whose fire acceptance is incomplete still counts as putting the works into use. The correct approach is to trial only within the scope already accepted, with a written temporary fire plan and fire watch staff present throughout the trial.