The classic handover-day dispute
A 15-year lease ends. The lessor demands: demolish the entire workshop, level the ground, return “vacant land” as on day one. The tenant objects: the workshop is still perfectly usable — why make me pay to tear it down? The standoff drags on, and late handover penalties accrue daily.
The 2015 Civil Code (Article 482) requires the tenant to return leased property in the condition received, ordinary wear and tear excepted — and to restore the original state if alterations were made without the lessor’s consent. But what does “condition as received” mean for a workshop the tenant itself built? The answer is in your contract.
Three scenarios and who pays
Scenario 1 — The contract is explicit: the best case. Standard contracts carry a handover clause: either the tenant demolishes at its cost, or the lessor takes over the works (possibly offset against rent/deposit or purchased at an agreed price). Follow the signed clause — that simple.
Scenario 2 — The contract is silent: the general principle applies: a tenant that built on leased land must demolish, restore the site and bear the cost at term end, unless the lessor agrees to take over. Rationale: the land must come back unencumbered for the landowner’s full disposition.
Scenario 3 — The lessor wants to keep the workshop: negotiate the works’ residual value. Engage an independent valuer; if no price is agreed, the tenant must still demolish per Scenario 2 — do not leave the works as an unwanted “gift” and then get billed storage fees.
Agree it upfront: four must-haves in a new lease
1. Handover option: demolish, or lessor takeover (and on what conditions). 2. Costs: who pays demolition, leveling, construction-waste disposal. 3. Timeline: how many days after expiry to complete handover; extension mechanics and late penalties. 4. Handover deposit: retain part of the deposit until demolition and site acceptance complete — the most practical lever to secure performance.
Frequently asked questions
If I don’t demolish, can the landowner demolish and bill me?
The landowner may not unilaterally demolish your property. Proper sequence: demand your performance → if you fail, sue for demolition plus cost compensation. Self-help demolition can make the landowner liable to compensate you for property damage.
My workshop was duly permitted — why demolish it?
A construction permit does not make the workshop the landowner’s asset. When the lease ends, your right to build on the land ends with it — unless a new contract/agreement allows continued existence.
What does demolition typically cost?
Depending on scale and structure, usually 3–8% of construction value for steel-frame workshops, higher for reinforced concrete or basement structures. Budget it when signing the lease.
Can I sell the workshop to the next tenant?
Yes, by tripartite agreement: you transfer the works to the incoming tenant while the landowner signs a fresh lease with them. This win-win-win is common in industrial parks.
What are the penalties for late handover?
Per the contract’s penalty clause (usually daily, rent-based). Even without a clause, the lessor may claim actual losses caused by late handover.
Related articles
- Suzhou and China's Parks vs Vietnam's VSIP for New Investors
- US Real Estate near Sensitive Sites: CFIUS Notes for Vietnamese Investors
- Can Foreigners Buy Property in Vietnam? Ownership Rules Explained
- The 30% Foreign Quota Per Apartment Building: What Buyers Must Know
- How to Check If a Building Still Has Foreign Quota Available
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.