Relocating a factory from China to Vietnam is a strategic decision spanning many quarters: the legal entity and remaining assets in China must be dealt with, while a new project must be established in Vietnam with full investment, land, environmental and labour licensing. The most costly risk usually lies not in transport costs, but in assets in China not being definitively resolved and machinery getting stuck at customs clearance.
Quick summary. Topic: relocating a factory from China to Vietnam — liquidating assets in China, importing used machinery, leasing land/industrial parks, investment incentives, bringing personnel to Vietnam. Audience: Chinese groups and businesses currently operating a factory in China. Points to check in advance: the plan for the legal entity in China, equipment import conditions, the form of land lease, incentive conditions, and the work permit plan.
1. Relocating a factory is a cross-border transaction, not a single procedure
Unlike a new establishment, a relocation always has two parallel legal ends. At the China end, the business must decide the fate of the existing legal entity — downsizing, transferring or dissolving it — while dealing with employment contracts, premises leases, tax obligations and outstanding receivables and payables. At the Vietnam end, a new legal entity/project must be established with an Investment Registration Certificate, enterprise registration, environmental and construction permits. The two ends are linked by the asset transfer flow: machinery, moulds, inventory of raw materials. If planning covers only the Vietnam end, the business may fall into a situation where the new factory is ready but the equipment cannot be exported because it is stuck in liquidation.
2. Dealing with the legal entity and remaining assets in China
Three common options for the company in China: downsizing to serve the domestic market or act as an R&D centre; transferring the whole or part of the business to a third party; or dissolving and fully liquidating. In particular, transferring machinery from the Chinese company to the Vietnamese company — even within the same group — is still an asset transfer transaction that must be valued, documented and tax-declared in China; a valuation below market value may be adjusted by the tax authority with arrears collected. Work with lawyers and tax advisers in both China and Vietnam.
3. Investment structure in Vietnam: new establishment or acquiring an existing facility
Two main choices. One is establishing a new enterprise under the Law on Investment No. 143/2025/QH15 (effective from 01/03/2026): register the establishment of the enterprise to be issued an Enterprise Registration Certificate (ERC) first, then carry out the procedure for an Investment Registration Certificate (IRC) under Article 72 of Decree No. 96/2026/ND-CP: design the project exactly to need with an opportunity to enjoy investment incentives, but the time to complete the site, construction and environmental and fire-prevention permits may extend to 12–24 months. Two is acquiring an operating business or subleasing ready-built factory premises in an industrial park: shortening the time to operation but requiring careful due diligence on land, permits, outstanding tax obligations and labour disputes. See also Setting up a subsidiary for a Chinese group and M&A in Vietnam for foreign investors.
4. Importing used machinery: conditions and dossiers
This is the stage most prone to congestion. Vietnamese law permits the import of used machinery, equipment and technological lines but applies strict conditions — and the conditions for a technological line differ from those for individual machines, so list the two separately from the outset. For production lines covered by Article 5 of Circular No. 56/2026/TT-BKHCN (in force from 5 September 2026), 85% refers to remaining capacity or efficiency relative to design specifications. For machines and equipment covered by Article 6 of the same Circular, equipment age generally must not exceed 10 years (counted from the year of manufacture to the year of import); specific fields in Appendix I allow higher limits (up to 15 or 20 years) — check the applicable standards for the relevant goods group; some equipment groups on the prohibited list may not be imported. Decision No. 18/2019/QD-TTg now applies only to transitional cases under Article 17 of Circular 56/2026/TT-BKHCN (applications and inspection certificates received or issued before 5 September 2026). The dossier must prove the year of manufacture (labels, original technical documents), the operating condition and the purpose of use for the licensed project. The solution: inventory and classify equipment early — separating technological lines from individual machines, and the group that qualifies from the group that must be liquidated; check Articles 5 and 6, the appendices and any special procedures before relying on an example; prepare the dossier proving the year of manufacture before signing the transport contract. Detailed conditions may be adjusted from period to period, so compare them against the regulations in force before signing the contract.
5. Leasing land and factory premises in industrial parks
Three main forms of site access: subleasing land in an industrial park from the infrastructure investor (the most common; the term is tied to the remaining land use term of the industrial park project; rent is paid once or annually); leasing ready-built factory premises (fast to operate, but the construction permit, fire-prevention acceptance and sublease terms must be checked); receiving a project transfer or acquiring a business leasing land in an industrial park (due diligence is needed on the lease rights, remaining financial obligations and the ability to adjust the project’s objectives). Under the Law on Land 2024, the land use term for an investment project is at most 50 years (70 years in special cases); extension upon expiry is not automatic. Details at Leasing industrial park land for Chinese investors and Industrial real estate and industrial parks.
6. Investment incentives: conditions for enjoyment and common misunderstandings
Corporate income tax incentives and land rent exemption/reduction are what make Vietnam attractive, but incentives are not automatic. Under the Law on Investment No. 143/2025/QH15 and its guiding instruments, incentives apply by business line, location and project scale, and must be recorded in the Investment Registration Certificate. Three common misunderstandings: every manufacturing project in an industrial park receives incentives (in reality many industrial parks lie outside incentive locations); incentives apply right from the establishment of the company (in reality incentives are tied to the project and the time taxable income arises); and not factoring in the obligation to maintain the incentive conditions throughout the enjoyment period. Advice: put the incentive conditions into the project proposal dossier from the start, instead of requesting supplementation after licensing.
7. Environmental, construction and fire-prevention permits
Three key groups of permits before operation: the environmental permit, the factory construction permit, and fire-prevention acceptance. For a relocation project there are two particular points. First, the line transferred from China must be described truthfully in the environmental dossier — capacity, raw materials, waste, chemicals. Second, the schedule of these permits is usually the project’s critical path; a factory that has not passed fire-prevention acceptance may not operate.
8. Bringing the Chinese management team and experts to Vietnam
Most relocation projects need to bring the core team from China: the factory’s board of directors, technology engineers, operations experts during the installation and transfer stage. Each person needs a work permit (or confirmation of exemption from a work permit), a suitable visa/temporary residence card, and a personal income tax compliance plan — including tax obligations in China during the overseas assignment and the application of the Vietnam–China double taxation agreement. The correct roadmap: sign an employment contract or an internal secondment decision, obtain approval of the need to use foreign labour, and file the work permit dossier at least a few weeks before the intended entry date. Details at Compliance for Chinese managers working in Vietnam and Labour law advice.
9. Tax and customs during the relocation
The flow of assets and capital creates many tax touchpoints. At the equipment import stage: import tax by HS code and origin (equipment from China may enjoy preferential rates under an FTA with a suitable certificate of origin), and import VAT. At the operation stage: corporate income tax with investment incentives (if eligible), contractor tax on payments to Chinese organisations providing services or machinery with installation. At the transfer pricing stage: transactions buying and selling equipment and raw materials between the parent company in China and the subsidiary in Vietnam are related-party transactions and must comply with the rules on determining related-party transaction prices (Decree No. 255/2026/ND-CP, effective from 01/7/2026). At the divestment stage: liquidating remaining assets in China or repatriating profits requires tax calculation in China and application of the double taxation agreement. See also Tax compliance for Chinese businesses in Vietnam and Tax advice for FDI businesses.
10. Contracts during the transition stage
During the 12–18 months of transition, the business manages contracts in both countries simultaneously: liquidating or transferring premises leases, raw material supply contracts and employment contracts in China; signing new construction, installation, supply and logistics contracts in Vietnam. Two groups of clauses need careful review: the termination and compensation clauses in contracts in China — early termination of a long-term lease or exclusive supply contract may give rise to significant penalty fees, so negotiate a termination roadmap instead of unilaterally cancelling; and the factory construction contract in Vietnam — clearly prescribe acceptance standards, schedules tied to permit milestones, late-progress penalties and warranties. For contracts signed with a Chinese counterparty for performance in Vietnam, use a bilingual Vietnamese–Chinese contract with a clause determining the prevailing language version in case of conflict. See Vietnam–China processing and purchase contracts and Vietnam–China commercial contracts.
11. Common risks that make projects overrun on cost or schedule
First, underestimating procedure time: from the investment decision to stable operation usually takes 18–30 months. Second, equipment not qualifying for import — a technical inventory is needed before signing the transport contract. Third, a site that is "clean on paper but stuck in reality": the industrial park investor has not completed its financial obligations to the State, or the remaining lease term is too short compared with the depreciation cycle. Fourth, supply chain disruption during the transition stage — overlapping supply contracts of at least 3–6 months are needed. Fifth, no budget provision for compliance costs: legal and tax advice and permit adjustments often account for a significant proportion that the initial financial plan overlooks.
12. Suggested implementation roadmap by stage
Stage 0 — feasibility assessment (2–3 months): survey industrial parks and sites, technical inventory of equipment in China, assess incentive conditions, build the overall financial model. Stage 1 — legal structure (3–6 months): decide the fate of the legal entity in China, obtain the Investment Registration Certificate and establish the enterprise in Vietnam, sign the land/factory lease contract, start the environmental and fire-prevention procedures. Stage 2 — transfer (6–12 months): export/liquidate assets in China, import and clear equipment through customs, install the line, obtain work permits and bring the core team over. Stage 3 — parallel operation and closing the China end (6–12 months): trial runs and commercial operation in Vietnam while maintaining minimum production in China to secure orders, then complete liquidation, tax finalisation and termination of remaining obligations.
FAQ
How long does relocating a factory from China to Vietnam usually take?
Usually 18–30 months from the investment decision to stable operation, including investment procedures, land/factory leasing, equipment import and installation, environmental – fire-prevention permits and recruitment.
Can used machinery be imported into Vietnam?
Yes, but the conditions differ by group: for technological lines under Article 5, 85% means remaining capacity or efficiency relative to design specifications; for machines under Article 6, check the applicable age limit and technical standards for the goods group; equipment on the prohibited list may not be imported.
Should the legal entity in China be retained after relocation?
It depends on the strategy: many groups retain the Chinese legal entity to serve the domestic market or act as an R&D centre, while moving export production to Vietnam.
Does a relocation project enjoy investment incentives in Vietnam?
It may, if it meets the conditions on business line, location and scale under the Law on Investment No. 143/2025/QH15 and is recorded in the Investment Registration Certificate.
When should a lawyer be engaged in a relocation project?
Right from the feasibility assessment stage, to design the two-end structure and build the procedure timeline.
Talk to FLAT LAW FIRM
If your business is considering relocating a factory from China to Vietnam, FLAT LAW FIRM provides support in Vietnamese, Chinese and English: legal feasibility assessment, two-end investment structuring, equipment import procedures, land/industrial park leasing and investment incentives. Please contact us for advice on your specific situation.