When site clearance compensation for an industrial park doubles against the original estimate — a new land price table, residents rejecting the compensation plan, additional crops, graves and structures to pay for — the question “who bears the increase” is answered not by the Land Law but by the land lease and sublease contract between the company and the infrastructure developer. Land Law 31/2024/QH15, with compensation principles in Article 91 and its chapter on compensation, support and resettlement, governs the State’s relationship with landholders whose land is recovered and with the project owner; between two businesses, the allocation is pure civil-contract risk sharing. The piece on site clearance disputes in FDI projects (FDI-LC-2355) addresses the relationship with affected residents; this one addresses the sublessee-developer relationship.
Reading the park lease: three clause patterns decide everything
Pattern one, the “all-in rent including compensation” clause: rent and infrastructure fees are the entire cost of receiving cleared land, and the developer bears all clearance cost movements. Under this pattern the increase is the developer’s, and the company must simply avoid signing any annex “acknowledging shared arising costs” under schedule pressure. Pattern two, rent “excluding the actual compensation difference”: the contract splits rent into a fixed part and a compensation part settled at actual cost — the increase defaults onto the company, and the only real fight is verifying that the costs are genuine and reasonable.
Pattern three, silence: the contract says nothing about compensation movements. The outcome then turns on contract interpretation rules and the original negotiation record — quotations, working minutes and park marketing materials promising “cleared land” are strong evidence that the developer bears it.
The developer’s responsibilities in the clearance chain
The park developer is the party allocated or leased the land by the State to build infrastructure, and is normally the focal point advancing funds and coordinating the compensation organisation. Its duties include transparency of the project compensation plan, handover of cleared land on the schedule promised in the sublease, and not shifting its own financial obligations onto the sublessee absent a contract clause. Where handover is late because compensation rose, the sublessee may demand adjustment of its own milestones, fee relief for the period before handover, and damages where the contract penalises late handover.
What sublessees must avoid is signing partial handover minutes recording “received in full” while the remaining area is still uncleared — such minutes can be used to sever claims over the park-wide schedule.
Residents, negotiation and the litigation route
A secondary sublessee is not the compensating party toward residents; any “negotiation with residents” is supplementary support outside the official plan (employment support, early relocation support) and must be documented as voluntary support to avoid setting a precedent for individualised demands. The worst move is paying households directly outside the compensation organisation: the payment is neither recognised in project costs nor compatible with a uniform compensation level across the park.
On litigation: the company sues the infrastructure developer on the sublease, in court or in arbitration if the contract so provides, seeking a declaration that the increase is not its obligation plus damages for late handover. Suing residents or the State’s compensation decision is not the sublessee’s route, unless the company is itself the project owner whose land is recovered.
FAQ
How should an industrial park land lease contract be drafted?
The contract must state one of two mechanisms expressly: all-in rent covering the entire site clearance compensation (developer bears movements), or settlement at actual cost with the sublessee’s right to verify vouchers. Add a cleared-land handover deadline, late-handover sanctions, and a bar on the developer shifting arising costs to the sublessee through any annex not signed by the sublessee.
What responsibilities does the industrial park developer have?
The infrastructure developer is responsible for organising and advancing compensation within the allocated project, coordinating with the state compensation body, and handing over cleared land on the schedule committed in the sublease. It may not unilaterally pass increased compensation costs to the subleasing company where the contract contains no sharing mechanism.
How to negotiate with local residents?
A secondary sublessee does not negotiate compensation in the State’s place; to accelerate progress it should only add documented supplementary support (employment or early-relocation support) channelled through the project’s compensation organisation. Paying households directly outside the plan is not recognised in project costs and breaks the uniform compensation level.
Can I sue?
Yes — against the infrastructure developer under the sublease, in court or in arbitration per the dispute clause, seeking a declaration that the increase is not the company’s obligation and damages for late handover. A secondary sublessee does not sue residents over the State’s compensation plan.
Related articles
- BT Projects and Payment in Land Funds: The New Mechanism After the Amended PPP Law and Unblocking Resolutions
- Land Allocation and Leasing via Land-Use-Right Auctions: The New Process and Participation Conditions for FDI Enterprises
- Subdividing and Merging Land Plots in Vietnam: Minimum Area Conditions
- Appealing Land Recovery Decisions in Vietnam: Procedures and Administrative Lawsuits
- Suing Over Low Site-Clearance Compensation in Vietnam: Revaluation Demands
This legal analysis has been verified against current Vietnamese regulations and cross-border FDI transaction practices by the attorneys at FLAT LAW FIRM.